PRPL202210118
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Plumbing Rough-in Inspection | Partial Pass | 2/14/2023 (2:30 - 3:30) | 2/14/2023 (PM) | 02/14/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
02/14/2023
Air test on all under ground sanitary
Air test on all under ground flammable waste
Flam tank and elevator sump not dug in
|
||||
| Plumbing Rough-in Inspection | Not Ready | 2/15/2023 (2:30 - 3:30) | 2/15/2023 (PM) | 02/15/2023 |
| Plumbing Rough-in Inspection | Partial Pass | 5/23/2023 (8:00 - 10:00) | 5/23/2023 (AM) | 05/23/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
05/23/2023
Visual inspection of flammable waste interceptor okay. Manometer test still needed on it.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 6/15/2023 (12:30 - 2:30) | 6/15/2023 (PM) | 06/15/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/15/2023
Visual plumbing rough-in inspection ok for units on 4th floor from North end to fire door.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 6/20/2023 (12:30 - 2:30) | 6/20/2023 (PM) | 06/20/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/20/2023
Visual rough in plumbing ok for 12 units from fire door towards the South on 4th floor. Doorways are signed off for visual inspection.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 6/22/2023 (12:30 - 2:30) | 6/22/2023 (PM) | 06/22/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/22/2023
Rough plumbing visual inspection ok for units 4th floor.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 6/26/2023 (10:00 - 12:00) | 6/26/2023 (AM) | 06/26/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/26/2023
Plumbing rough in visuals complete for all units on 4th floor.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 6/29/2023 (10:00 - 12:00) | 6/29/2023 (AM) | 06/29/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/29/2023
Visual inspection for 3rd floor units rough in plumbing.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 7/6/2023 (12:30 - 2:30) | 7/6/2023 (PM) | 07/06/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/06/2023
Visual plumbing rough in inspection ok for first 11 units from North end to fire door on 3rd floor.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 7/11/2023 (12:30 - 2:30) | 7/11/2023 (PM) | 07/11/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/11/2023
Visual plumbing rough in inspection ok for the next 11 units on 3rd floor.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 7/13/2023 (10:00 - 12:00) | 7/13/2023 (AM) | 07/13/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/13/2023
Visual rough in plumbing ok for units 325-332.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 7/17/2023 (10:00 - 12:00) | 7/17/2023 (AM) | 07/17/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/17/2023
Visual plumbing rough in inspection ok for remaining units on 3rd floor 333-346.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 7/27/2023 (10:00 - 12:00) | 7/27/2023 (PM) | 07/27/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/27/2023
Visual plumbing inspection good for units 201-213.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 8/1/2023 (10:00 - 12:00) | 8/1/2023 (AM) | 08/01/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/01/2023
Visual for rough plumbing in units 210-220 is good.
|
||||
| Plumbing Rough-in Inspection | Passed | 8/2/2023 (10:00 - 12:00) | 8/2/2023 (AM) | 08/02/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/02/2023
Visual for rough plumbing in units 221-232 are good.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 8/3/2023 (10:00 - 12:00) | 8/3/2023 (AM) | 08/03/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/03/2023
Visual inspection for rough in plumbing on all of 2nd floor is complete and two model units on 1st floor are good.
Notch out studs where needed above pvc pipes running horizontal thru studs for building setting and pvc expansion/contraction.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 8/23/2023 (10:00 - 12:00) | 8/23/2023 (AM) | 08/23/2023 |
| Plumbing Rough-in Inspection | Passed | 8/24/2023 (10:00 - 12:00) | 8/24/2023 (AM) | 08/24/2023 |
| Plumbing Rough-in Inspection | Partial Pass | 8/28/2023 (10:00 - 12:00) | 8/28/2023 (AM) | 08/28/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/28/2023
Visual inspection of rough plumbing on remaining units on 1st floor okay.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 8/30/2023 (8:00 - 10:00) | 8/30/2023 (AM) | 08/30/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/30/2023
Air tests for a portion of units on the north and west side of building okay.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 9/7/2023 (8:00 - 10:00) | 9/7/2023 (AM) | 09/07/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/07/2023
Air tests for portion of units okay. Schedule more air test for remaining units when ready.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 9/14/2023 (12:30 - 2:30) | 9/14/2023 (PM) | 09/14/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/14/2023
Remaining air tests for rough sanitary waste and vent piping okay.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 9/20/2023 (8:00 - 10:00) | 9/20/2023 (AM) | 09/20/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/20/2023
Air tests on remaking waste and vent piping, and a portion of rainwater drain/overflow piping on south and east side of building okay.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 10/4/2023 (8:00 - 10:00) | 10/4/2023 (AM) | 10/04/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/04/2023
Visual inspection and air tests of a portion roof drains, overflow roof drains, and associated piping okay.
|
||||
| Plumbing Rough-in Inspection | Passed | 10/9/2023 (10:00 - 12:00) | 10/9/2023 (AM) | 10/09/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/09/2023
Remaining air tests for roof drains, over flow roof drains, and associated piping okay.
|
||||
| Plumbing Final Inspection | Partial Pass | 1/8/2024 (12:30 - 2:30) | 1/8/2024 (PM) | 01/08/2024 |
|
Corrections:
Miscellaneous/Other
Comment Only
01/08/2024
Monometers look good.
|
||||
| Plumbing Final Inspection | Partial Pass | 1/9/2024 (12:30 - 2:30) | 1/9/2024 (PM) | 01/09/2024 |
|
Corrections:
Miscellaneous/Other
Comment Only
01/09/2024
Remaining manometer tests for southern half of building okay. Only the small middle east/west running hallway still needed.
|
||||
| Plumbing Final Inspection | Partial Pass | 1/10/2024 (12:30 - 2:30) | 1/10/2024 (PM) | 01/10/2024 |
|
Corrections:
Miscellaneous/Other
Outstanding
01/10/2024
Sent correction items to plumber on site.
|
||||
| Plumbing Final Inspection | Partial Pass | 1/11/2024 (12:30 - 2:30) | 1/11/2024 (PM) | 01/11/2024 |
|
Corrections:
Miscellaneous/Other
Comment Only
01/11/2024
Middle wing monometer was good. Walk-through in units on floor 1 through 4 look good as well.
|
||||
| Plumbing Final Inspection | Passed | 1/19/2024 (8:00 - 10:00) | 1/19/2024 (AM) | 01/19/2024 |
|
Corrections:
Miscellaneous/Other
Comment Only
01/19/2024
Looks good on final walk through.
|
||||