Permit Application Status

PRPL202213423


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRPL202213423
Plumbing
Finaled
GROSS ALFRED A
Other
Complete plumbing system for new 125 unit apartment building.
10/25/2022
02/28/2023
09/10/2024
03/14/2024

Locations

Permits

Permit Number: PRPL202213423

Plumbing
Finaled
02/28/2023
09/10/2024

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Plumbing Rough-in Inspection Partial Pass 5/15/2023 (2:30 - 3:30) 5/15/2023 (PM) 05/15/2023
Corrections:


Miscellaneous/Other
Comment Only
05/15/2023
Visual inspection and air test okay for underground flammable waste from area drains and associated piping.

Plumbing Rough-in Inspection Not Ready 5/16/2023 (8:00 - 10:00) 5/16/2023 (AM) 05/16/2023
Plumbing Rough-in Inspection Partial Pass 5/16/2023 (2:30 - 3:30) 5/16/2023 (PM) 05/16/2023
Corrections:


Miscellaneous/Other
Comment Only
05/16/2023
Visual inspection and air test okay for portion of underground waste/vent piping. May proceed and cover.

Plumbing Rough-in Inspection Partial Pass 5/17/2023 (8:00 - 10:00) 5/17/2023 (AM) 05/17/2023
Corrections:


Miscellaneous/Other
Comment Only
05/17/2023
Visual inspection on elevator pit drain piping.

Plumbing Rough-in Inspection Partial Pass 5/17/2023 (2:30 - 3:30) 5/17/2023 (PM) 05/17/2023
Corrections:


Miscellaneous/Other
Comment Only
05/17/2023
Air test okay on elevator pit drain piping.

Plumbing Rough-in Inspection Partial Pass 7/25/2023 (10:00 - 12:00) 7/25/2023 (AM) 07/25/2023
Plumbing Rough-in Inspection Partial Pass 8/23/2023 (10:00 - 12:00) 8/23/2023 (AM) 08/23/2023
Corrections:


Miscellaneous/Other
Comment Only
08/23/2023
Visual inspection and air test okay for model unit 520. Air tests okay for overflow roof drains and piping on south, east, and north side of building.

Plumbing Rough-in Inspection Partial Pass 8/30/2023 (12:30 - 2:30) 8/30/2023 (PM) 08/30/2023
Corrections:


Miscellaneous/Other
Comment Only
08/30/2023
Air tests okay for all portions of primary roof drains and piping terminating in garage, and over flow roof drains terminating through a sidewalk. Will need air test on horizontal storm piping in garage when completed.

Plumbing Rough-in Inspection Partial Pass 9/6/2023 (10:00 - 12:00) 9/6/2023 (AM) 09/06/2023
Corrections:


Miscellaneous/Other
Comment Only
09/06/2023
Air tests for sanitary waste and vent piping in units in long south to north corridor okay except for units 116 and 117. Find leaks and provide 5lb. air test for 15 minutes. Also change all short turn 90’s used for sanitary drainage in the horizontal position to long turn 90’s.

Plumbing Rough-in Inspection Partial Pass 9/7/2023 (10:00 - 12:00) 9/7/2023 (AM) 09/07/2023
Corrections:


Miscellaneous/Other
Comment Only
09/07/2023
Air test for portion of units is west and north side of building. Still need air tests for 3 remaining unit stacks.

Plumbing Rough-in Inspection Partial Pass 9/12/2023 (10:00 - 12:00) 9/12/2023 (AM) 09/12/2023
Corrections:


Miscellaneous/Other
Comment Only
09/12/2023
Remaining air tests for units okay.

Plumbing Rough-in Inspection Partial Pass 9/25/2023 (8:00 - 10:00) 9/25/2023 (AM) 09/25/2023
Corrections:


Miscellaneous/Other
Comment Only
09/25/2023
Visual inspection of 4th floor rough plumbing okay.

Plumbing Rough-in Inspection Partial Pass 10/3/2023 (8:00 - 10:00) 10/3/2023 (AM) 10/03/2023
Corrections:


Miscellaneous/Other
Comment Only
10/03/2023
Visual inspection of all rough plumbing on 3rd floor okay.

Plumbing Rough-in Inspection Partial Pass 10/17/2023 (8:00 - 10:00) 10/17/2023 (AM) 10/17/2023
Corrections:


Miscellaneous/Other
Comment Only
10/17/2023
Visual inspection of rough plumbing on second floor. Okay.

Plumbing Rough-in Inspection Partial Pass 10/31/2023 (12:30 - 2:30) 10/31/2023 (PM) 10/31/2023
Corrections:


Miscellaneous/Other
Comment Only
10/31/2023
Visual inspection of 1st floor rough plumbing okay.

Plumbing Final Inspection Partial Pass 2/26/2024 (12:30 - 2:30) 2/26/2024 (PM) 02/26/2024
Corrections:


Miscellaneous/Other
Comment Only
02/26/2024
Monometer is good on 1/2 the building.

Miscellaneous/Other
Comment Only
02/26/2024
Monometer is good on 1/2 the building.

Plumbing Final Inspection Partial Pass 2/28/2024 (12:30 - 2:30) 2/28/2024 (PM) 02/28/2024
Corrections:


Miscellaneous/Other
Comment Only
02/28/2024
Manometers is good. Fifth floor visual on fixtures being sealed is good.

Plumbing Final Inspection Partial Pass 3/12/2024 (10:00 - 12:00) 3/12/2024 (AM) 03/12/2024
Corrections:


Miscellaneous/Other
Comment Only
03/12/2024
Third and fourth floor visual on plumbing looks good.

Plumbing Final Inspection Passed 3/14/2024 (10:00 - 12:00) 3/14/2024 (AM) 03/14/2024
Corrections:


Miscellaneous/Other
Comment Only
03/14/2024
First and second floor fixtures are sealed and look good.