PRPL202300248
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Plumbing Rough-in Inspection | Passed | 1/18/2023 (10:00 - 12:00) | 1/18/2023 (AM) | 01/18/2023 |
Corrections:
Miscellaneous/Other
Comment Only
01/18/2023
Visual and air test on new waste and vent piping for new sink.
|
||||
Plumbing Final Inspection | Partial Pass | 4/14/2023 (12:30 - 2:30) | 4/14/2023 (PM) | 04/14/2023 |
Corrections:
Miscellaneous/Other
Comment Only
04/14/2023
Install hammer arrestor on hot water line serving dishwasher, and secure drain hose from dishwasher at a higher point within cabinet.
|
||||
Plumbing Final Inspection | Passed | 04/18/2023 |