Permit Application Status

PRPL202301381


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRPL202301381
Plumbing
Finaled
BLOOMINGTON QOZ VENTURES LLC
Other
Complete plumbing system in new 242 unit building.
02/14/2023
02/27/2023
04/28/2025
10/30/2024

Locations

Permits

Permit Number: PRPL202301381

Plumbing
Finaled
02/27/2023
04/28/2025

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Plumbing Rough-in Inspection Partial Pass 7/31/2023 (12:30 - 2:30) 7/31/2023 (PM) 07/31/2023
Plumbing Rough-in Inspection Partial Pass 8/1/2023 (Afternoon) 8/1/2023 (PM) 08/01/2023
Corrections:


Miscellaneous/Other
Comment Only
08/01/2023
Visual inspection of underground sanitary waste piping, flammable waste piping, and flammable waste interceptor on south side of building okay. Contractor will provide air test as more underground gets completed.

Plumbing Rough-in Inspection Partial Pass 8/2/2023 (12:30 - 2:30) 8/2/2023 (PM) 08/02/2023
Corrections:


Miscellaneous/Other
Comment Only
08/02/2023
Visual inspection and air test on underground sanitary waste piping and flammable waste piping okay.

Plumbing Rough-in Inspection Partial Pass 8/3/2023 (10:00 - 12:00) 8/3/2023 (AM) 08/03/2023
Plumbing Rough-in Inspection Partial Pass 8/28/2023 (12:30 - 2:30) 8/28/2023 (PM) 08/28/2023
Corrections:


Miscellaneous/Other
Comment Only
08/28/2023
Visual inspection and air tests on remaining portion of underground waste piping okay.

Plumbing Rough-in Inspection Partial Pass 1/11/2024 (8:00 - 10:00) 1/11/2024 (AM) 01/11/2024
Corrections:


Miscellaneous/Other
Comment Only
01/11/2024
With contractor. They will be scheduling more inspections in the upcoming days as a project moves along.

Plumbing Rough-in Inspection Partial Pass 1/16/2024 (2:30 - 3:30) 1/16/2024 (PM) 01/16/2024
Corrections:


Miscellaneous/Other
Comment Only
01/16/2024
Air test on roof drains in parking garage is good. Drains are for East Plaza south roof.

Plumbing Rough-in Inspection Partial Pass 1/23/2024 (8:00 - 10:00) 1/23/2024 (AM) 01/23/2024
Corrections:


Miscellaneous/Other
Comment Only
01/23/2024
Visual inspection and air test of portion of a rwl overflow okay. Air tests on units and n 1st-6th floor on southwest side of building okay.

Plumbing Rough-in Inspection Partial Pass 1/23/2024 (2:30 - 3:30) 1/23/2024 (PM) 01/23/2024
Plumbing Rough-in Inspection Partial Pass 1/24/2024 (8:00 - 10:00) 1/24/2024 (AM) 01/24/2024
Corrections:


Miscellaneous/Other
Comment Only
01/24/2024
Visual inspection and air test for rwl piping in northwest section of garage okay. Air tests for 1st-6th floor units on the south, and west side of building okay.

Plumbing Rough-in Inspection Partial Pass 1/24/2024 (2:30 - 3:30) 1/24/2024 (PM) 01/24/2024
Corrections:


Miscellaneous/Other
Comment Only
01/24/2024
Visual inspection of remaining rwl piping and air tests okay. Air tests on dwv piping in northwest corner for 1st-6th floor units okay.

Plumbing Rough-in Inspection Partial Pass 1/25/2024 (8:00 - 10:00) 1/25/2024 (AM) 01/25/2024
Corrections:


Miscellaneous/Other
Comment Only
01/25/2024
Air tests for 1st-6th floor units on north side of building okay.

Plumbing Rough-in Inspection Partial Pass 1/30/2024 (2:30 - 3:30) 1/30/2024 (PM) 01/30/2024
Corrections:


Miscellaneous/Other
Comment Only
01/30/2024
Air test OK on stacks in north east corner. Venting on half of six floor looks okay also.

Plumbing Final Inspection Partial Pass 9/5/2024 (12:30 - 2:30) 02/08/2024
Corrections:


Miscellaneous/Other
Comment Only
02/08/2024
Waste and vent on sixth floor northwest side looks good.

Plumbing Rough-in Inspection Partial Pass 2/8/2024 (8:00 - 10:00) 2/8/2024 (AM) 02/08/2024
Corrections:


Miscellaneous/Other
Carried Forward
02/20/2024
Piping on sixth floor on northwest side looks good.

Plumbing Rough-in Inspection Partial Pass 2/27/2024 (8:00 - 10:00) 2/27/2024 (AM) 02/27/2024
Corrections:


Miscellaneous/Other
Carried Forward
03/05/2024
Piping on sixth floor on northwest side looks good.

Plumbing Rough-in Inspection Partial Pass 3/5/2024 (8:00 - 10:00) 3/5/2024 (AM) 03/05/2024
Corrections:


Miscellaneous/Other
Comment Only
03/05/2024
Visual inspection of rough plumbing on remaining units on 5th floor okay.

Plumbing Rough-in Inspection Partial Pass 3/11/2024 (10:00 - 12:00) 3/11/2024 (AM) 03/11/2024
Corrections:


Miscellaneous/Other
Comment Only
03/11/2024
Ruff in visual on fourth floor Southside OK.

Plumbing Rough-in Inspection Partial Pass 3/14/2024 (10:00 - 12:00) 3/14/2024 (AM) 03/14/2024
Corrections:


Miscellaneous/Other
Comment Only
03/14/2024
Fourth floor waste and vent visual OK.

Plumbing Rough-in Inspection Partial Pass 3/19/2024 (10:00 - 12:00) 3/19/2024 (AM) 03/19/2024
Plumbing Rough-in Inspection Partial Pass 3/21/2024 (10:00 - 12:00) 3/21/2024 (AM) 03/21/2024
Corrections:


Miscellaneous/Other
Comment Only
03/21/2024
Rest of third-floor rough and visual looks good.

Plumbing Rough-in Inspection Partial Pass 4/2/2024 (10:00 - 12:00) 4/2/2024 (AM) 04/02/2024
Corrections:


Miscellaneous/Other
Comment Only
04/02/2024
Half of second floor, waste, and vent on southside look good.

Plumbing Rough-in Inspection Partial Pass 4/4/2024 (10:00 - 12:00) 4/4/2024 (AM) 04/04/2024
Corrections:


Miscellaneous/Other
Comment Only
04/04/2024
Waste and vent visual on second floor northside looks good.

Plumbing Rough-in Inspection Partial Pass 4/22/2024 (8:00 - 10:00) 4/22/2024 (AM) 04/22/2024
Corrections:


Miscellaneous/Other
Comment Only
04/22/2024
First floor southside waste vent piping visual looks good.

Plumbing Final Inspection Not Ready 9/18/2024 (12:30 - 2:30) 9/18/2024 (PM) 09/18/2024
Plumbing Final Inspection Partial Pass 9/19/2024 (10:00 - 12:00) 9/19/2024 (AM) 09/19/2024
Corrections:


Miscellaneous/Other
Comment Only
09/19/2024
Monometer test are good. Schedule for visual on units once fixtures are sealed.

Plumbing Final Inspection Partial Pass 10/2/2024 (10:00 - 12:00) 10/2/2024 (AM) 10/02/2024
Corrections:


Miscellaneous/Other
Outstanding
10/02/2024
All dishwashers need their own stops. Unit 619 caulk shower valve Unit 623 no visible clean out for island vent in wall. Caulk the diverter plates on hand held showers. Unit 630 no visible clean out for island vent. Check other units that have island kitchens. To make sure cleanout are visible.

Plumbing Final Inspection Partial Pass 10/3/2024 (10:00 - 12:00) 10/3/2024 (AM) 10/03/2024
Corrections:


Miscellaneous/Other
Comment Only
10/03/2024
On completion of fifth floor walk-through today corrections were sent to plumbing foreman.

Plumbing Final Inspection Partial Pass 10/8/2024 (10:00 - 12:00) 10/8/2024 (AM) 10/08/2024
Corrections:


Miscellaneous/Other
Comment Only
10/08/2024
Raise dishwasher drain lines in units. Air gap must be up as high as possible underneath the countertop.

Plumbing Final Inspection Partial Pass 10/9/2024 (10:00 - 12:00) 10/9/2024 (AM) 10/09/2024
Corrections:


Miscellaneous/Other
Comment Only
10/09/2024
Third floor 323 – expose clean out on island vent stack in wall. 304 – raise dishwasher drain line in cabinet. It is too low. 300 – raise dishwasher drain line. Too low. ?

Plumbing Final Inspection Partial Pass 10/10/2024 (10:00 - 12:00) 10/10/2024 (AM) 10/10/2024
Corrections:


Miscellaneous/Other
Comment Only
10/10/2024
Second floor 242-dap toilet to wall and bolt toilet to floor 236 – kitchen and bathroom vanity not complete Finish installing dishwasher stops.

Plumbing Rough-in Inspection Passed 4/25/2024 (8:00 - 10:00) 4/25/2024 (AM) 10/18/2024
Plumbing Final Inspection Partial Pass 10/22/2024 (12:30 - 2:30) 10/22/2024 (PM) 10/22/2024
Corrections:


Miscellaneous/Other
Comment Only
10/22/2024
First floor/ 123 – no visible clean out for island vent in cabinet Install dishwasher stops in all units.

Plumbing Final Inspection Partial Pass 10/24/2024 (10:00 - 12:00) 10/24/2024 (AM) 10/24/2024
Corrections:


Miscellaneous/Other
Comment Only
10/24/2024
Air test on piping for ice melt looks good. want to see information on flushometer valves installed on first floor.

Plumbing Final Inspection Passed 10/30/2024 (10:00 - 12:00) 10/30/2024 (AM) 10/30/2024