PRPL202303998
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Plumbing Rough-in Inspection | Partial Pass | 5/9/2023 (8:00 - 10:00) | 5/9/2023 (AM) | 05/09/2023 |
Corrections:
Miscellaneous/Other
Comment Only
05/09/2023
Visual inspection and air test on underground waste piping for bathrooms and kitchenette okay.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 05/12/2023 | ||
Corrections:
Miscellaneous/Other
Comment Only
05/12/2023
Visual inspection and air test area drains and piping routed to flammable waste interceptor okay. Manometer test on flammable waste interceptor okay.
|
||||
Plumbing Final Inspection | Not Ready | 5/12/2023 (8:00 - 10:00) | 5/12/2023 (AM) | 05/12/2023 |
Plumbing Final Inspection | Passed | 09/12/2023 |