PRPL202304798
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Plumbing Rough-in Inspection | Passed | 6/5/2023 (8:00 - 10:00) | 6/5/2023 (AM) | 06/05/2023 |
Corrections:
Miscellaneous/Other
Comment Only
06/05/2023
Visual inspection and air test okay for all aboveground rough plumbing.
|
||||
Plumbing Final Inspection | Partial Pass | 8/31/2023 (8:00 - 10:00) | 8/31/2023 (AM) | 08/31/2023 |
Corrections:
Miscellaneous/Other
Comment Only
08/31/2023
Final visual inspection and manometer test okay. Contractor will finish covering water heater pvc intake and exhaust piping passing through return air plenum.
|
||||
Plumbing Final Inspection | Passed | 08/31/2023 | ||
Corrections:
Miscellaneous/Other
Comment Only
08/31/2023
Water heater intake/exhaust are now wrapped in insulation which conforms to the requirements needed to pass through the return air plenum.
|