PRPL202304866
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Plumbing Rough-in Inspection | Partial Pass | 05/15/2023 | ||
Corrections:
Miscellaneous/Other
Comment Only
05/15/2023
Visual inspection and air test on underground waste piping okay.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 6/20/2023 (12:30 - 2:30) | 6/20/2023 (PM) | 06/20/2023 |
Corrections:
Miscellaneous/Other
Comment Only
06/20/2023
Visual inspection of in wall rough plumbing okay.
|
||||
Plumbing Final Inspection | Passed | 7/24/2023 (12:30 - 2:30) | 7/24/2023 (PM) | 07/24/2023 |