Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Plumbing Rough-in Inspection | Partial Pass | 9/6/2023 (8:00 - 10:00) | 9/6/2023 (AM) | 09/06/2023 |
Corrections:
Miscellaneous/Other
Comment Only
09/06/2023
Visual inspection and air test okay for above floor rough plumbing.
|
||||
Plumbing Rough-in Inspection | Passed | 9/15/2023 (8:00 - 10:00) | 9/15/2023 (AM) | 09/15/2023 |
Corrections:
Miscellaneous/Other
Comment Only
09/15/2023
Inspection of under floor horizontal waste and vent piping okay.
|
||||
Plumbing Final Inspection | Partial Pass | 10/24/2023 (10:00 - 12:00) | 10/24/2023 (AM) | 10/24/2023 |
Corrections:
Miscellaneous/Other
Comment Only
10/24/2023
Final visual inspection okay. Will close permit when pictures of completed mopsink submitted.
|
||||
Plumbing Final Inspection | Passed | 11/17/2023 (8:00 - 10:00) | 11/17/2023 (AM) | 11/17/2023 |