PRPL202312239
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Plumbing Rough-in Inspection | Partial Pass | 10/18/2023 (8:00 - 10:00) | 10/18/2023 (AM) | 10/18/2023 |
Corrections:
Miscellaneous/Other
Comment Only
10/18/2023
Visual inspection of in wall and portion under floor waste and vent piping for new bathroom okay. Air test to be performed at a future inspection.
|
||||
Plumbing Rough-in Inspection | Passed | 12/13/2023 (12:30 - 2:30) | 12/13/2023 (PM) | 12/13/2023 |
Plumbing Final Inspection | Passed | 6/24/2024 (12:30 - 2:30) | 6/24/2024 (PM) | 06/24/2024 |
Corrections:
Miscellaneous/Other
Comment Only
06/24/2024
Fixtures look good. Water heater has not been replaced. Will need inspection when it is done.
|