PRPL202312328
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Plumbing Rough-in Inspection | Passed | 10/25/2023 (8:00 - 10:00) | 10/25/2023 (AM) | 10/25/2023 |
Plumbing Final Inspection | Partial Pass | 11/2/2023 (8:00 - 10:00) | 11/2/2023 (AM) | 11/02/2023 |
Partial pass on condition, the indirect waste issue is being addressed. | ||||
Plumbing Final Inspection | Passed | 11/8/2023 (8:00 - 10:00) | 11/8/2023 (AM) | 11/08/2023 |