PRPL202400678
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Plumbing Final Inspection | Pending | |||
| Plumbing Rough-in Inspection | Partial Pass | 3/5/2024 (8:00 - 10:00) | 3/5/2024 (AM) | 03/05/2024 |
|
Corrections:
Miscellaneous/Other
Comment Only
03/05/2024
Visual inspection of rough valves in rooms on 8th floor okay
|
||||
| Plumbing Final Inspection | Partial Pass | 4/9/2024 (10:00 - 12:00) | 4/9/2024 (AM) | 04/09/2024 |
|
Corrections:
Miscellaneous/Other
Comment Only
04/09/2024
Visual final for 8th floor okay except for 2 suites not yet completed
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 4/30/2024 (8:00 - 10:00) | 4/30/2024 (AM) | 04/30/2024 |
| Plumbing Final Inspection | Partial Pass | 6/14/2024 (12:30 - 2:30) | 6/14/2024 (PM) | 06/14/2024 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/14/2024
Visual final for seventh floor complete.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 11/5/2024 (8:00 - 10:00) | 11/5/2024 (AM) | 11/05/2024 |
| Plumbing Rough-in Inspection | Partial Pass | 11/8/2024 (8:00 - 10:00) | 11/8/2024 (AM) | 11/08/2024 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/08/2024
5th floor Ri is good to go.
Must cap off all sewer gas opening on 5th floor
|
||||
| Plumbing Final Inspection | Partial Pass | 12/23/2024 (12:30 - 2:30) | 12/23/2024 (PM) | 12/23/2024 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/23/2024
No water on will check with 4th floor RI next Monday
|
||||
| Plumbing Final Inspection | Partial Pass | 1/10/2025 (10:00 - 12:00) | 1/10/2025 (AM) | 01/10/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
01/10/2025
needs toilet caps and seals on tub to floor
also toilet valve covers
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 1/10/2025 (10:00 - 12:00) | 1/10/2025 (AM) | 01/10/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
01/10/2025
ALL OPEN PLUMBING PIPES NEED TO BE SEALED OFF!!!
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 1/28/2025 (12:30 - 2:30) | 1/28/2025 (PM) | 01/28/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
01/28/2025
Ri are good down to 4th floor, floor 4 still needs RI
|
||||
| Plumbing Final Inspection | Partial Pass | 1/28/2025 (2:30 - 3:30) | 1/28/2025 (PM) | 01/28/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
01/28/2025
6th floor is good to go, but one unit 682 is still waiting for big tub that is back ordered will need inspection when ready
|
||||
|
Miscellaneous/Other
Comment Only
01/28/2025
Floor 5 has a few things left to do 576,572,564 and 552
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 2/6/2025 (8:00 - 10:00) | 2/6/2025 (AM) | 02/06/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
02/06/2025
Toilets are fixed on 5
|
||||
| Plumbing Final Inspection | Partial Pass | 3/20/2025 (12:30 - 2:30) | 3/20/2025 (PM) | 03/20/2025 |
| Floor 4 | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
03/20/2025
458 leaking toilet, missing face plate on shower
456 need ADA toilet
455 needs toilet re-dap
459 leak on cap.
461 needs toilet re-dap
|
||||
| Plumbing Final Inspection | Partial Pass | 4/8/2025 (10:00 - 12:00) | 4/8/2025 (AM) | 04/08/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
04/08/2025
Still need to finish the corner suites on 8,6 and 4.
|
||||