PRPL202401438
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Plumbing Rough-in Inspection | Partial Pass | 5/30/2024 (12:30 - 2:30) | 5/30/2024 (PM) | 05/30/2024 |
Pressure tested for Grease Interceptor passed plumbing hooking up to grease Interceptor passed still need RI on bathrooms and other work | ||||
Plumbing Rough-in Inspection | Partial Pass | 7/10/2024 (8:00 - 10:00) | 7/10/2024 (AM) | 07/10/2024 |
Corrections:
Miscellaneous/Other
Comment Only
07/10/2024
Both underground’s hold on air test
Still need about ground RI when ready
|
||||
Plumbing Rough-in Inspection | Partial Pass | 8/1/2024 (10:00 - 12:00) | 8/1/2024 (AM) | 08/01/2024 |
Corrections:
Miscellaneous/Other
Comment Only
08/01/2024
Above ground waste vent on kitchen and bathrooms looks good with 5 pound air test.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 8/13/2024 (8:00 - 10:00) | 8/13/2024 (AM) | 08/13/2024 |
Corrections:
Miscellaneous/Other
Comment Only
08/13/2024
still need above-ground RI when ready
|
||||
Plumbing Rough-in Inspection | Passed | 8/15/2024 (2:30 - 3:30) | 8/15/2024 (PM) | 08/15/2024 |
Plumbing Final Inspection | Partial Pass | 10/11/2024 (10:00 - 12:00) | 10/11/2024 (AM) | 10/11/2024 |
Still have one more sink, and floor drain cover to finish | ||||
Corrections:
Miscellaneous/Other
Comment Only
10/11/2024
Watts 1in RP M# LF009M2QT S# 263971
Tester # BT747716 William is good till 12-31-2025
Test passed, Unit was last tested on 9-27-2024
|
||||
Plumbing Final Inspection | Not Ready | 10/16/2024 (10:00 - 12:00) | 10/16/2024 (AM) | 10/16/2024 |
Plumbing Final Inspection | Passed | 10/21/2024 | ||
Corrections:
All corrections have been made.
Comment Only
10/21/2024
All corrections have been made.
|