PRPL202404052
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Plumbing Rough-in Inspection | Partial Pass | 4/23/2024 (8:00 - 10:00) | 4/23/2024 (AM) | 04/23/2024 |
Corrections:
Miscellaneous/Other
Comment Only
04/23/2024
Need to finish drain pipe for sink. will check out water heater that finish
|
||||
Plumbing Rough-in Inspection | Passed | 04/26/2024 | ||
Corrections:
Miscellaneous/Other
Comment Only
04/26/2024
Pictures of completed work are approved
|
||||
Plumbing Final Inspection | Passed | 6/6/2024 (12:30 - 2:30) | 6/6/2024 (PM) | 06/06/2024 |