Summary

PRPL202407610
Plumbing
Issued
BLMGTN SCHOOL DIST #271
Alteration/Repair/Replace
Replacing domestic water lines, replacing plumbing fixtures and adding restrooms. Only schedule Dave or Jesse for plumbing inspections (Due to delegation agreement) (State Review Attached)
06/12/2024
06/17/2024
12/14/2025
08/27/2024

Locations

Permits

Permit Number: PRPL202407610

Plumbing
Issued
06/17/2024
12/14/2025

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Plumbing Final Inspection Pending
Plumbing Rough-in Inspection Pending
Plumbing Rough-in Inspection Partial Pass 6/20/2024 (8:00 - 10:00) 6/20/2024 (AM) 06/20/2024
Corrections:


Miscellaneous/Other
Comment Only
06/20/2024
Plumbing underground looks good air test look good.

Plumbing Rough-in Inspection Partial Pass 7/2/2024 (8:00 - 10:00) 7/2/2024 (AM) 07/02/2024
Corrections:


Miscellaneous/Other
Comment Only
07/02/2024
Piping underground on dish room and single bathroom are good along with 5 pound air test. Individual venting in classrooms on sink and bubblers is OK.

Plumbing Rough-in Inspection Partial Pass 7/8/2024 (8:00 - 10:00) 7/8/2024 (AM) 07/08/2024
Corrections:


Miscellaneous/Other
Comment Only
07/08/2024
Visual inspection and air tests okay for bank of lavs and both restroom groups.

Plumbing Rough-in Inspection Partial Pass 7/23/2024 (2:30 - 3:30) 7/23/2024 (PM) 07/23/2024
Corrections:


Miscellaneous/Other
Comment Only
07/23/2024
Visual inspection and air tests for bathroom, sink, eyewash, and floor drains in penthouse okay

Plumbing Final Inspection Partial Pass 8/21/2024 (10:00 - 12:00) 8/21/2024 (AM) 08/22/2024
Corrections:


Miscellaneous/Other
Comment Only
08/22/2024
Final visual inspections and manometer tests okay. Still need visual final for kitchen area.

Plumbing Rough-in Inspection Partial Pass 6/16/2025 (AM) 06/16/2025
Corrections:


Miscellaneous/Other
Comment Only
06/16/2025
Plumbing inspection on underground in area B with air test is good. One bathroom group 2 inch stack for floor drains in mechanical room on roof

Plumbing Final Inspection Partial Pass 8/27/2024 (10:00 - 12:00) 8/27/2024 (AM) 06/17/2025
Corrections:


Miscellaneous/Other
Comment Only
08/27/2024
Final visual inspection and manometer test of plumbing in kitchen area okay.