Permit Application Status

PRPL202413101


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRPL202413101
Plumbing
Permit(s) Issued
BLOOMINGTON EVER COMMERCIAL LLC
Other
complete plumbing system for 208 unit apt building.
10/03/2024
10/14/2024
09/08/2026

Locations

Permits

Permit Number: PRPL202413101

Plumbing
Issued
10/14/2024
09/08/2026

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Plumbing Rough-in Inspection Partial Pass 1/8/2025 (10:00 - 12:00) 1/8/2025 (AM) 01/08/2025
underground
Corrections:


Miscellaneous/Other
Comment Only
01/08/2025
Flammable waste and sanitary underground on east side with 5 pound air test looks good.

Plumbing Rough-in Inspection Partial Pass 1/9/2025 (8:00 - 10:00) 1/9/2025 (AM) 01/09/2025
underground
Corrections:


Miscellaneous/Other
Comment Only
01/09/2025
Installation of storm on east side underground looks good with air test.

Plumbing Rough-in Inspection Partial Pass 1/13/2025 (2:30 - 3:30) 1/13/2025 (PM) 01/13/2025
Corrections:


Miscellaneous/Other
Comment Only
01/13/2025
Rest of underground piping complete on west side. Want to see air test on broken 6 inch pipe.

Plumbing Rough-in Inspection Partial Pass 1/14/2025 (8:00 - 10:00) 1/14/2025 (AM) 01/14/2025
Plumbing Rough-in Inspection Partial Pass 4/1/2025 (12:30 - 2:30) 4/1/2025 (PM) 04/01/2025
Plumbing Rough-in Inspection Partial Pass 5/6/2025 (2:30 - 3:30) 5/6/2025 (PM) 05/06/2025
Corrections:


Miscellaneous/Other
Comment Only
05/06/2025
Air test for portion of unit stacks okay.

Plumbing Rough-in Inspection Partial Pass 5/7/2025 (10:00 - 12:00) 5/7/2025 (AM) 05/07/2025
Corrections:


Miscellaneous/Other
Comment Only
05/07/2025
Air test for portion of unit stacks looks good.

Plumbing Rough-in Inspection Partial Pass 5/8/2025 (8:00 - 10:00) 5/8/2025 (AM) 05/08/2025
Corrections:


Miscellaneous/Other
Comment Only
05/08/2025
Air test for portion of unit stacks all looks good.

Plumbing Rough-in Inspection Partial Pass 5/12/2025 (12:30 - 2:30) 5/12/2025 (PM) 05/12/2025
Corrections:


Miscellaneous/Other
Comment Only
05/12/2025
Air test for portion of unit stacks looks good.

Plumbing Rough-in Inspection Partial Pass 5/13/2025 (10:00 - 12:00) 5/13/2025 (AM) 05/13/2025
Corrections:


Miscellaneous/Other
Comment Only
05/13/2025
Air tests for remaining unit piping okay. Air tests for a portion of storm piping above garage okay. Air test still need on remaining storm piping risers above garage.

Plumbing Rough-in Inspection Partial Pass 5/14/2025 (10:00 - 12:00) 5/14/2025 (AM) 05/14/2025
Corrections:


Miscellaneous/Other
Comment Only
05/14/2025
Air test at rest of rain leaders in parking garage looks good.

Plumbing Rough-in Inspection Partial Pass 5/21/2025 (12:30 - 2:30) 5/21/2025 (PM) 05/21/2025
Corrections:


Miscellaneous/Other
Comment Only
05/21/2025
Visual on piping in wall on fifth floor southwest side to firewall.

Plumbing Rough-in Inspection Partial Pass 6/4/2025 (10:00 - 12:00) 6/4/2025 (AM) 06/04/2025
Corrections:


Miscellaneous/Other
Comment Only
06/04/2025
Fifth floor visual on plumbing is complete.

Plumbing Rough-in Inspection Partial Pass 6/18/2025 (10:00 - 12:00) 6/18/2025 (AM) 06/18/2025
Corrections:


Miscellaneous/Other
Comment Only
06/18/2025
Visuals on fourth floor east side and first floor unit 115 and 117 are OK.

Plumbing Rough-in Inspection Partial Pass 7/2/2025 (10:00 - 12:00) 7/2/2025 (AM) 07/02/2025
Corrections:


Miscellaneous/Other
Comment Only
07/02/2025
Visual on rough-in plumbing fourth floor West side looks good.

Plumbing Rough-in Inspection Partial Pass 7/15/2025 (12:30 - 2:30) 7/15/2025 (PM) 07/15/2025
Corrections:


Miscellaneous/Other
Comment Only
07/15/2025
Visual on third floor east side of waste and vent looks good.

Plumbing Rough-in Inspection Partial Pass 7/30/2025 (10:00 - 12:00) 7/30/2025 (AM) 07/30/2025
3rd floor inspection
Corrections:


Miscellaneous/Other
Comment Only
07/30/2025
Visual on piping on third floor west side all looks good.

Plumbing Rough-in Inspection Partial Pass 8/6/2025 (10:00 - 12:00) 8/6/2025 (AM) 08/06/2025
Corrections:


Miscellaneous/Other
Comment Only
08/06/2025
Rough-ins on second floor east side look good.

Plumbing Rough-in Inspection Partial Pass 8/18/2025 (2:30 - 3:30) 8/18/2025 (PM) 08/19/2025
Corrections:


Miscellaneous/Other
Carried Forward
08/20/2025
Piping on second floor west side looks good.

Plumbing Rough-in Inspection Partial Pass 8/25/2025 (8:00 - 10:00) 8/25/2025 (AM) 08/25/2025
Corrections:


Miscellaneous/Other
Comment Only
08/25/2025
Air test on garage plumbing West side is good.

Plumbing Rough-in Inspection Partial Pass 8/25/2025 (12:30 - 2:30) 8/25/2025 (PM) 08/25/2025
Corrections:


Miscellaneous/Other
Resolved
08/25/2025
Piping on second floor west side looks good.

Miscellaneous/Other
Comment Only
08/25/2025
Visual on plumbing first floor. B is good.

Plumbing Rough-in Inspection Partial Pass 8/26/2025 (2:30 - 3:30) 8/26/2025 (PM) 08/26/2025
Corrections:


Miscellaneous/Other
Comment Only
08/26/2025
Air test on stacks north Northwest area B look good.

Plumbing Final Inspection Partial Pass 08/27/2025
Corrections:


Miscellaneous/Other
Comment Only
08/27/2025
Visual and plumbing in area a is good.

Plumbing Rough-in Inspection Partial Pass 8/27/2025 (3:30 - 4:00) 8/27/2025 (PM) 08/27/2025
Corrections:


Miscellaneous/Other
Comment Only
08/27/2025
Air test on rest of plumbing stacks of building look good.

Progress Inspection Partial Pass 2/3/2026 (10:00 - 12:00) 2/3/2026 (AM) 02/03/2026
pneumometer Inspection
Corrections:


Miscellaneous/Other
Comment Only
02/03/2026
Manometer test on stacks 132 ,140,142 and 144 approved

Progress Inspection Partial Pass 2/4/2026 (10:00 - 12:00) 2/4/2026 (AM) 02/04/2026
Corrections:


Miscellaneous/Other
Comment Only
02/04/2026
Monometer good on stacks 148,150-149,147,143,141,139,128,138,136,126,131,129

Plumbing Final Inspection Partial Pass 2/10/2026 (12:30 - 2:30) 2/10/2026 (PM) 02/10/2026
Corrections:


Miscellaneous/Other
Comment Only
02/10/2026
Manometer on plumbing stacks, complete and approved.

Plumbing Final Inspection Partial Pass 2/18/2026 (10:00 - 12:00) 2/18/2026 (AM) 02/18/2026
Corrections:


Miscellaneous/Other
Comment Only
02/18/2026
Manometers don’t inflammable waste in basement parking garage approved. Fifth floor visuals on units on east side approved.

Plumbing Final Inspection Partial Pass 2/19/2026 (10:00 - 12:00) 2/19/2026 (AM) 02/19/2026
Corrections:


Miscellaneous/Other
Comment Only
02/19/2026
Visual on fifth floor units west side approved.

Plumbing Final Inspection Partial Pass 2/23/2026 (10:00 - 12:00) 2/23/2026 (AM) 02/23/2026
Corrections:


Miscellaneous/Other
Comment Only
02/23/2026
Forth floor east wing units approved.

Plumbing Final Inspection Partial Pass 2/20/2026 (10:00 - 12:00) 2/20/2026 (AM) 02/23/2026
Plumbing Final Inspection Partial Pass 2/25/2026 2/25/2026 (PM) 02/25/2026
Corrections:


Miscellaneous/Other
Comment Only
02/25/2026
Plumbing approved in units on 4th floor area A and 3rd floor area B.

Plumbing Final Inspection Partial Pass 2/26/2026 (12:30 - 2:30) 2/26/2026 (PM) 02/26/2026
Corrections:


Miscellaneous/Other
Comment Only
02/26/2026
Visuals on fixtures from third floor area A to second floor area B approved.

Plumbing Final Inspection Partial Pass 3/3/2026 (Afternoon) 3/3/2026 (PM) 03/03/2026
Corrections:


Miscellaneous/Other
Comment Only
03/03/2026
Visuals on 2B and 1A complete.

Plumbing Final Inspection Partial Pass 3/4/2026 (Morning) 3/4/2026 (AM) 03/04/2026
Corrections:


Miscellaneous/Other
Comment Only
03/04/2026
Visuals of plumbing fixtures and units complete and approved. Still waiting for inspection on RPZ’s once they have been tested and tagged.

Plumbing Final Inspection VOID 3/12/2026 (8:00 - 10:00) 03/12/2026
Corrections:


Miscellaneous/Other
Comment Only
05/08/2025
Air test for portion of unit stacks all looks good.

Plumbing Final Inspection Passed 3/12/2026 (8:00 - 10:00) 03/12/2026
Corrections:


Miscellaneous/Other
Comment Only
03/12/2026
RPZ‘s have been tested and put into service.

Plumbing Rough-in Inspection Passed 8/27/2025 (8:00 - 10:00) 8/27/2025 (AM) 03/12/2026