PRPL202414202
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Plumbing Final Inspection | Pending | |||
| Underground Plumbing Inspection | Pending | |||
| Progress Inspection | Pending | |||
| Plumbing Rough-in Inspection | Pending | |||
| Plumbing Rough-in Inspection | Partial Pass | 12/16/2024 (12:30 - 2:30) | 12/16/2024 (PM) | 12/16/2024 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/16/2024
East side P1 LL zone 1
Air test on underground holds and piping meets code. Okay to cover.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 1/2/2025 (8:00 - 10:00) | 1/2/2025 (AM) | 01/02/2025 |
| underground | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
01/02/2025
Piping for acid waste,trench drains on underground in P1 lower level looks good with 5 pound air test.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 1/28/2025 (10:00 - 12:00) | 1/28/2025 (AM) | 01/28/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
01/28/2025
Visual inspection and air tests for floor drain piping and bathroom group okay.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 2/20/2025 (8:00 - 10:00) | 2/20/2025 (AM) | 02/20/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
02/20/2025
Venting for acid waste in P1 with 5 pound air test looks good.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 2/25/2025 (10:00 - 12:00) | 2/25/2025 (AM) | 02/25/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
02/25/2025
Piping underground for storm on east side with 5 pound air test looks good to cover.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 5/13/2025 (12:30 - 2:30) | 5/13/2025 (PM) | 05/13/2025 |
| Plumbing Final Inspection | Partial Pass | 5/13/2025 (12:30 - 2:30) | 5/13/2025 (PM) | 05/13/2025 |
| Underground Plumbing Inspection | Partial Pass | 5/20/2025 (8:00 - 10:00) | 5/20/2025 (AM) | 05/20/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
05/20/2025
Underground on P2 loading dock with sump basin. Air test is good.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 6/25/2025 (10:00 - 12:00) | 6/25/2025 (AM) | 06/25/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/25/2025
P – one first floor bathroom remodel looks good.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 7/17/2025 (12:30 - 2:30) | 7/17/2025 (PM) | 07/17/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/17/2025
Inspection of roof drains and piping on East side of new building okay.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 8/4/2025 (12:30 - 2:30) | 8/4/2025 (PM) | 08/04/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/04/2025
Air test on roof drains in P1 loading dock is good.
|
||||
| Progress Inspection | Partial Pass | 9/2/2025 (10:00 - 12:00) | 9/2/2025 (AM) | 09/02/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/02/2025
Bathroom fixtures look good.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 11/6/2025 (8:00 - 10:00) | 11/6/2025 (AM) | 11/06/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/06/2025
Air test on roof drains near elevator approved in area one. Progress inspection also is good.
|
||||