Permit Application Status

PRPL202416562


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRPL202416562
Plumbing
Finaled
700 AMERICAN LLLP
Other
Complete plumbing system in new 128 unit apartment.
12/23/2024
12/26/2024
06/21/2026
12/23/2025

Locations

Permits

Permit Number: PRPL202416562

Plumbing
Finaled
12/26/2024
06/21/2026

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Plumbing Final Inspection Pending
Corrections:


Miscellaneous/Other
Comment Only
07/01/2025
Visual on rough-in plumbing on fourth floor area A is good.

Plumbing Rough-in Inspection Not Ready 3/31/2025 (2:30 - 3:30) 3/31/2025 (PM) 03/31/2025
Plumbing Rough-in Inspection Partial Pass 4/1/2025 (10:00 - 12:00) 4/1/2025 (AM) 04/01/2025
Corrections:


Miscellaneous/Other
Comment Only
04/01/2025
Underground piping all looks good on the sanitary and flammable waste. Air test looks good also.

Plumbing Rough-in Inspection Not Ready 4/1/2025 (2:30 - 3:30) 4/1/2025 (PM) 04/01/2025
Plumbing Rough-in Inspection Partial Pass 6/18/2025 (12:30 - 2:30) 6/18/2025 (PM) 06/18/2025
5th floor inspections
Corrections:


Miscellaneous/Other
Comment Only
06/18/2025
Air test on waste and vent stacks in area a is OK.

Plumbing Rough-in Inspection Partial Pass 6/24/2025 (10:00 - 12:00) 6/24/2025 (AM) 06/24/2025
Possible floor 4 & 5, will time allowing
Corrections:


Miscellaneous/Other
Comment Only
06/24/2025
Air test on stacks in area B is OK. Visual on in wall plumbing on fifth floor area a is good.

Plumbing Rough-in Inspection Partial Pass 6/30/2025 (8:00 - 10:00) 6/30/2025 (AM) 06/30/2025
5th Floor
Corrections:


Miscellaneous/Other
Comment Only
06/30/2025
Visual on in wall plumbing in area B fifth floor looks good.

Plumbing Rough-in Inspection Not Ready 7/1/2025 (8:00 - 10:00) 7/1/2025 (AM) 07/01/2025
rain, stormwater & air
Plumbing Rough-in Inspection Partial Pass 7/7/2025 (10:00 - 12:00) 7/7/2025 (AM) 07/07/2025
Corrections:


Miscellaneous/Other
Comment Only
07/07/2025
Air test on rainwater and overflows all look good.

Plumbing Rough-in Inspection Partial Pass 7/8/2025 (10:00 - 12:00) 7/8/2025 (AM) 07/08/2025
Corrections:


Miscellaneous/Other
Comment Only
07/08/2025
Plumbing rough-ins on fourth floor area B are good.

Plumbing Rough-in Inspection Partial Pass 7/21/2025 (8:00 - 10:00) 7/21/2025 (AM) 07/21/2025
Corrections:


Miscellaneous/Other
Comment Only
07/21/2025
Waste and vent visual on third floor area A looks good.

Plumbing Rough-in Inspection Failed 7/22/2025 (8:00 - 10:00) 7/22/2025 (AM) 07/22/2025
Corrections:


Miscellaneous/Other
Comment Only
07/22/2025
Third floor area B some units the horizontal wet vent is flat. Correct, and schedule another inspection.

Plumbing Rough-in Inspection Partial Pass 7/28/2025 (8:00 - 10:00) 7/28/2025 (AM) 07/28/2025
2nd floor rough-in
Corrections:


Miscellaneous/Other
Carried Forward
07/28/2025

Miscellaneous/Other
Comment Only
07/28/2025
Corrections on third floor are good. Two units on second floor area B the horizontal wet vent need to be fixed. send photos once complete.

Plumbing Rough-in Inspection Partial Pass 8/11/2025 (8:00 - 10:00) 8/11/2025 (AM) 08/11/2025
Corrections:


Miscellaneous/Other
Resolved
08/11/2025

Miscellaneous/Other
Comment Only
08/11/2025
Waste and vent piping on the second floor area looks good.

Plumbing Rough-in Inspection Passed 8/13/2025 (10:00 - 12:00) 8/13/2025 (AM) 08/13/2025
Corrections:


Miscellaneous/Other
Comment Only
08/13/2025
Visual on second floor. Contractor will send pictures after fixes.

Plumbing Rough-in Inspection Partial Pass 8/18/2025 (10:00 - 12:00) 8/18/2025 (AM) 08/18/2025
Corrections:


Miscellaneous/Other
Comment Only
08/18/2025
Air test on plumbing stacks in parking garage on north west side of building look good.

Plumbing Rough-in Inspection Partial Pass 8/19/2025 (10:00 - 12:00) 8/19/2025 (AM) 08/19/2025
Corrections:


Miscellaneous/Other
Comment Only
08/19/2025
Air test on second half of building plumbing stacks looks good.

Plumbing Rough-in Inspection Passed 8/20/2025 (8:00 - 10:00) 8/20/2025 (AM) 08/20/2025
Plumbing Rough-in Inspection Partial Pass 11/10/2025 (12:30 - 2:30) 11/10/2025 (PM) 11/10/2025
Corrections:


Miscellaneous/Other
Comment Only
11/10/2025
Walked fifth floor for visual on plumbing fixtures. Fixtures will need to be sealed on upcoming inspections.

Plumbing Rough-in Inspection Passed 11/12/2025 (10:00 - 12:00) 11/12/2025 (AM) 11/12/2025
Corrections:


Miscellaneous/Other
Resolved
11/12/2025

Plumbing Rough-in Inspection Passed 11/13/2025 (10:00 - 12:00) 11/13/2025 (AM) 11/13/2025
Corrections:


Miscellaneous/Other
Comment Only
11/13/2025
Third floor fixtures look good.

Plumbing Final Inspection Partial Pass 11/13/2025 (10:00 - 12:00) 11/13/2025
Corrections:


Miscellaneous/Other
Comment Only
11/13/2025
Fifth through third floor fixtures are sealed and so approved.

Plumbing Final Inspection Partial Pass 11/25/2025 (Afternoon) 11/25/2025 (PM) 11/25/2025
Corrections:


Miscellaneous/Other
Comment Only
11/25/2025
Manometer test is good on building. Walk-through’s on first and second floor still needed.

Plumbing Final Inspection Partial Pass 12/8/2025 (8:00 - 10:00) 12/8/2025 (AM) 12/08/2025
Corrections:


Miscellaneous/Other
Comment Only
12/08/2025
Finish sealing toilets on second floor. Secure dishwasher unit 201 Hook up supply to dishwasher in unit 1209

Plumbing Final Inspection Partial Pass 12/9/2025 (8:00 - 10:00) 12/9/2025 (AM) 12/09/2025
Corrections:


Miscellaneous/Other
Comment Only
12/09/2025
Call for reinspection on the rest of the units on first floor that were not ready. Toilets need to be set dishwashers need to be secured.

Plumbing Final Inspection Passed 12/23/2025 (12:30 - 2:30) 12/23/2025 (PM) 12/23/2025