| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Plumbing Final Inspection | Pending | |||
|
Corrections:
Miscellaneous/Other
Comment Only
07/01/2025
Visual on rough-in plumbing on fourth floor area A is good.
|
||||
| Plumbing Rough-in Inspection | Not Ready | 3/31/2025 (2:30 - 3:30) | 3/31/2025 (PM) | 03/31/2025 |
| Plumbing Rough-in Inspection | Partial Pass | 4/1/2025 (10:00 - 12:00) | 4/1/2025 (AM) | 04/01/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
04/01/2025
Underground piping all looks good on the sanitary and flammable waste. Air test looks good also.
|
||||
| Plumbing Rough-in Inspection | Not Ready | 4/1/2025 (2:30 - 3:30) | 4/1/2025 (PM) | 04/01/2025 |
| Plumbing Rough-in Inspection | Partial Pass | 6/18/2025 (12:30 - 2:30) | 6/18/2025 (PM) | 06/18/2025 |
| 5th floor inspections | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
06/18/2025
Air test on waste and vent stacks in area a is OK.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 6/24/2025 (10:00 - 12:00) | 6/24/2025 (AM) | 06/24/2025 |
| Possible floor 4 & 5, will time allowing | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
06/24/2025
Air test on stacks in area B is OK. Visual on in wall plumbing on fifth floor area a is good.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 6/30/2025 (8:00 - 10:00) | 6/30/2025 (AM) | 06/30/2025 |
| 5th Floor | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
06/30/2025
Visual on in wall plumbing in area B fifth floor looks good.
|
||||
| Plumbing Rough-in Inspection | Not Ready | 7/1/2025 (8:00 - 10:00) | 7/1/2025 (AM) | 07/01/2025 |
| rain, stormwater & air | ||||
| Plumbing Rough-in Inspection | Partial Pass | 7/7/2025 (10:00 - 12:00) | 7/7/2025 (AM) | 07/07/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/07/2025
Air test on rainwater and overflows all look good.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 7/8/2025 (10:00 - 12:00) | 7/8/2025 (AM) | 07/08/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/08/2025
Plumbing rough-ins on fourth floor area B are good.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 7/21/2025 (8:00 - 10:00) | 7/21/2025 (AM) | 07/21/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/21/2025
Waste and vent visual on third floor area A looks good.
|
||||
| Plumbing Rough-in Inspection | Failed | 7/22/2025 (8:00 - 10:00) | 7/22/2025 (AM) | 07/22/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/22/2025
Third floor area B some units the horizontal wet vent is flat. Correct, and schedule another inspection.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 7/28/2025 (8:00 - 10:00) | 7/28/2025 (AM) | 07/28/2025 |
| 2nd floor rough-in | ||||
|
Corrections:
Miscellaneous/Other
Carried Forward
07/28/2025
|
||||
|
Miscellaneous/Other
Comment Only
07/28/2025
Corrections on third floor are good. Two units on second floor area B the horizontal wet vent need to be fixed. send photos once complete.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 8/11/2025 (8:00 - 10:00) | 8/11/2025 (AM) | 08/11/2025 |
|
Corrections:
Miscellaneous/Other
Resolved
08/11/2025
|
||||
|
Miscellaneous/Other
Comment Only
08/11/2025
Waste and vent piping on the second floor area looks good.
|
||||
| Plumbing Rough-in Inspection | Passed | 8/13/2025 (10:00 - 12:00) | 8/13/2025 (AM) | 08/13/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/13/2025
Visual on second floor. Contractor will send pictures after fixes.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 8/18/2025 (10:00 - 12:00) | 8/18/2025 (AM) | 08/18/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/18/2025
Air test on plumbing stacks in parking garage on north west side of building look good.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 8/19/2025 (10:00 - 12:00) | 8/19/2025 (AM) | 08/19/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/19/2025
Air test on second half of building plumbing stacks looks good.
|
||||
| Plumbing Rough-in Inspection | Passed | 8/20/2025 (8:00 - 10:00) | 8/20/2025 (AM) | 08/20/2025 |
| Plumbing Rough-in Inspection | Partial Pass | 11/10/2025 (12:30 - 2:30) | 11/10/2025 (PM) | 11/10/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/10/2025
Walked fifth floor for visual on plumbing fixtures. Fixtures will need to be sealed on upcoming inspections.
|
||||
| Plumbing Rough-in Inspection | Passed | 11/12/2025 (10:00 - 12:00) | 11/12/2025 (AM) | 11/12/2025 |
|
Corrections:
Miscellaneous/Other
Resolved
11/12/2025
|
||||
| Plumbing Rough-in Inspection | Passed | 11/13/2025 (10:00 - 12:00) | 11/13/2025 (AM) | 11/13/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/13/2025
Third floor fixtures look good.
|
||||
| Plumbing Final Inspection | Partial Pass | 11/13/2025 (10:00 - 12:00) | 11/13/2025 | |
|
Corrections:
Miscellaneous/Other
Comment Only
11/13/2025
Fifth through third floor fixtures are sealed and so approved.
|
||||
| Plumbing Final Inspection | Partial Pass | 11/25/2025 (Afternoon) | 11/25/2025 (PM) | 11/25/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/25/2025
Manometer test is good on building. Walk-through’s on first and second floor still needed.
|
||||
| Plumbing Final Inspection | Partial Pass | 12/8/2025 (8:00 - 10:00) | 12/8/2025 (AM) | 12/08/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/08/2025
Finish sealing toilets on second floor.
Secure dishwasher unit 201
Hook up supply to dishwasher in unit 1209
|
||||
| Plumbing Final Inspection | Partial Pass | 12/9/2025 (8:00 - 10:00) | 12/9/2025 (AM) | 12/09/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/09/2025
Call for reinspection on the rest of the units on first floor that were not ready. Toilets need to be set dishwashers need to be secured.
|
||||
| Plumbing Final Inspection | Passed | 12/23/2025 (12:30 - 2:30) | 12/23/2025 (PM) | 12/23/2025 |