PRPL202506983
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Plumbing Rough-in Inspection | Pending | |||
Corrections:
Miscellaneous/Other
Outstanding
08/14/2025
Visual Inspection and air test for underground waste piping bathrooms okay.
|
||||
Plumbing Final Inspection | Pending | 10/8/2025 (8:00 - 10:00) | 10/8/2025 (AM) | |
Plumbing Rough-in Inspection | Partial Pass | 6/25/2025 (8:00 - 10:00) | 6/25/2025 (AM) | 06/25/2025 |
Corrections:
Miscellaneous/Other
Carried Forward
06/25/2025
Visual Inspection and air test for underground waste piping bathrooms okay.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 7/8/2025 (8:00 - 10:00) | 7/8/2025 (AM) | 07/08/2025 |
Corrections:
Miscellaneous/Other
Carried Forward
07/08/2025
Visual Inspection and air test for underground waste piping bathrooms okay.
|
||||
Miscellaneous/Other
Comment Only
07/08/2025
Ri for wall in front bathrooms are done and hold air
|
||||
Plumbing Rough-in Inspection | Partial Pass | 7/22/2025 (8:00 - 10:00) | 7/22/2025 (AM) | 07/22/2025 |
Corrections:
Miscellaneous/Other
Carried Forward
07/22/2025
Visual Inspection and air test for underground waste piping bathrooms okay.
|
||||
Miscellaneous/Other
Comment Only
07/22/2025
Set 2 bathrooms RI good to go
|
||||
Plumbing Rough-in Inspection | Partial Pass | 8/14/2025 (8:00 - 10:00) | 8/14/2025 (AM) | 08/14/2025 |
Corrections:
Miscellaneous/Other
Carried Forward
08/14/2025
Visual Inspection and air test for underground waste piping bathrooms okay.
|
||||
Plumbing Final Inspection | Partial Pass | 8/14/2025 (8:00 - 10:00) | 8/14/2025 (AM) | 08/14/2025 |
Corrections:
Miscellaneous/Other
Comment Only
08/14/2025
First two bathroom areas on main floor are completed and tested with manometer.
|
||||
Plumbing Final Inspection | Partial Pass | 8/21/2025 (8:00 - 10:00) | 8/21/2025 (AM) | 08/21/2025 |
Plumbing Rough-in Inspection | Partial Pass | 9/8/2025 (8:00 - 10:00) | 9/8/2025 (AM) | 09/08/2025 |