PRPL202514309
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Plumbing Final Inspection | Pending | 5/21/2026 (10:00 - 12:00) | 5/21/2026 (AM) | |
| Plumbing Rough-in Inspection | Partial Pass | 1/20/2026 (12:30 - 2:30) | 1/20/2026 (PM) | 01/20/2026 |
|
Corrections:
Miscellaneous/Other
Comment Only
01/20/2026
Inspection and air test underground waste and vent piping okay. Schedule when ready for aboveground inspections.
|
||||
| Plumbing Rough-in Inspection | Passed | 1/30/2026 (8:00 - 10:00) | 1/30/2026 (AM) | 01/30/2026 |
|
Corrections:
Miscellaneous/Other
Comment Only
01/30/2026
Piping in wall and 5 pound air test is approved.
|
||||
| Plumbing Final Inspection | Passed | 3/16/2026 (10:00 - 12:00) | 3/16/2026 (AM) | 03/16/2026 |
| Underground Plumbing Inspection | Failed | 4/16/2026 (12:30 - 2:30) | 4/16/2026 (PM) | 04/16/2026 |
|
Corrections:
Miscellaneous/Other
Carried Forward
04/16/2026
Vent floor sink properly flat vent is not allowed.
|
||||
| Underground Plumbing Inspection | Passed | 5/21/2026 (10:00 - 12:00) | 04/17/2026 | |
|
Corrections:
Miscellaneous/Other
Outstanding
04/16/2026
Vent floor sink properly flat vent is not allowed.
|
||||
|
Miscellaneous/Other
Comment Only
04/17/2026
Pipe strapping and insulators have been installed on vent piping and waterlines.
|
||||