Summary

PRST201700464
Structural
Finaled
BLOOMINGTON CENTRAL STATION LLC
Alteration/Remodel
Not Required
Improvements include revisions to existing loading dock to facilitate new site layout that includes a pedestrain ramp for access to south parking lot.
02/10/2017
02/14/2017
05/21/2018

Locations

Permits

Permit Number: PRST201700464

Building
Finaled
02/14/2017
05/21/2018

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Structural Inspection Partial Pass 2/28/2017 (12:30 - 2:30) 2/28/2017 02/28/2017
REBAR INSPECTION - would like 12:30 - 1pm - has concrete coming.
Corrections:


See Document Markups
Comment Only
02/28/2017
See Document Markups: grid 5, B to C at loading dock. ( strip footings).

Structural Inspection Partial Pass 3/2/2017 (12:30 - 2:30) 3/2/2017 03/02/2017
Corrections:


See Document Markups
Comment Only
03/02/2017
See Document Markups... Rebar in formed wall at grid 5 A - B , and section of adjacent strip footing in loading dock. Approved for concrete placement.

Footing Inspection Partial Pass 3/16/2017 (12:30 - 2:30) 03/06/2017
Corrections:


Miscellaneous/Other
Comment Only
03/06/2017
foundation wall on line "1" grid "E-F" and 3 pads tied to existing footing in the loading dock. Approved for concrete placement.

Structural Inspection Partial Pass 3/6/2017 (12:30 - 2:30) 3/7/2017 03/07/2017
Corrections:


Miscellaneous/Other
Comment Only
03/07/2017
Two columns at loading dock, rebar as per plan design. Approved to form and pour concrete.

Structural Inspection Not Ready 3/8/2017 (12:30 - 2:30) 3/8/2017 03/08/2017
Corrections:


Miscellaneous/Other
Comment Only
03/08/2017
Progress.... no inspection needed yet.

Structural Inspection Partial Pass 3/13/2017 (8:00 - 10:00) 3/13/2017 03/13/2017
Corrections:


Miscellaneous/Other
Comment Only
03/13/2017
Rebar for compactor slab... rebar installed as per design plans, and added mat is installed over the existing conduits as per RFI design. Rebar mat will be lifted into concrete as it is placed.

Structural Inspection Partial Pass 3/14/2017 (12:30 - 2:30) 3/14/2017 03/14/2017
Corrections:


Miscellaneous/Other
Comment Only
03/14/2017
Section of wall at loading dock.. approved for concrete placement.

Footing Inspection Partial Pass 3/15/2017 (12:30 - 2:30) 3/15/2017 03/15/2017
Corrections:


Miscellaneous/Other
Comment Only
03/15/2017
Inspection of rebar in pad footing for relocation of loading dock at grid1, lines"E-H". Concrete had started to be placed prior to any inspection by special inspector or C.O.B. Stopped concrete and verified rebar where concrete was covered. All rebar accounted for and allowed to continue placement of concrete. All rebar in this footing pad is accounted for and correct, no other discrepancies found. Approved for full concrete placement.

Footing Inspection Partial Pass 3/16/2017 (12:30 - 2:30) 3/16/2017 03/16/2017
Corrections:


Miscellaneous/Other
Comment Only
03/16/2017
Retaining wall footing at loading dock... grid lines "H"-"L" including the 40ft footing coming out to the south near grid "K" location. Approved for concrete placement.

Structural Inspection Partial Pass 3/20/2017 (12:30 - 2:30) 03/21/2017
Corrections:


Miscellaneous/Other
Comment Only
03/21/2017
Poured wall section at loading dock retaining wall footing at grids "E-F" approved for concrete. Verbal corrections to contractor as to where clearance issues for the rebar are to be addressed. A.T. I . special inspections to look over and verify prior to concrete placement.

Progress Inspection Partial Pass 3/27/2017 (12:30 - 2:30) 03/22/2017
Corrections:


Miscellaneous/Other
Comment Only
03/22/2017
Wall section at retaining wall footing of loading dock area. Grid F-H. Ok to place concrete.

Structural Inspection Partial Pass 03/24/2017
Corrections:


Miscellaneous/Other
Comment Only
03/24/2017
Retaining wall section at new loading dock. Grid1- lines "H-K" . Approved for concrete placement.

Structural Inspection Partial Pass 3/27/2017 (12:30 - 2:30) 3/27/2017 03/27/2017
Corrections:


Miscellaneous/Other
Comment Only
03/27/2017
Retaining wall section at grid line1, K-L. Approved for concrete.

Structural Inspection Partial Pass 03/28/2017
Corrections:


Miscellaneous/Other
Comment Only
03/28/2017
Wall section of retaining wall: Lower section under the waste and rain water piping being set for pour. Rebar approved.

Structural Inspection Partial Pass 03/29/2017
Corrections:


Miscellaneous/Other
Comment Only
03/29/2017
Wall section at retaining wall footing approx at grid "K" see plans. Section 2/RLD02

Footing Inspection Partial Pass 03/30/2017
Corrections:


Miscellaneous/Other
Comment Only
03/30/2017
Strip footing inside of loading dock. Footing section outside of cut door opening. Reinforced slab on grade at loading dock. Approved for concrete.

Structural Inspection Partial Pass 03/31/2017
Corrections:


Miscellaneous/Other
Comment Only
03/31/2017
Footing for pedestrian bridge, approved for concrete. Poured wall sections on stoop footing and wall section for well area. Approved to pour concrete. Reinforced slab at loading dock on north section, approved.

Structural Inspection Partial Pass 04/03/2017
Corrections:


Miscellaneous/Other
Comment Only
04/03/2017
Poured wall sections at pedestrian bridge footing approved for concrete. Rebar for the slab embedment to wall will be wet sticker into concrete.

Structural Inspection Partial Pass 04/21/2017
Corrections:


Miscellaneous/Other
Comment Only
04/21/2017
Last upper section of retaining wall that was left out for removal and relocation of piping is being poured. Rebar installed as per plans. Strip footing located at the old entry of the loading dock is approved for concrete placement.

Structural Inspection Partial Pass 04/27/2017
Corrections:


Miscellaneous/Other
Comment Only
04/27/2017
First section of the reinforced slab on grade inside the existing loading dock approved for concrete placement.

Structural Inspection Partial Pass 05/02/2017
Corrections:


Miscellaneous/Other
Comment Only
05/02/2017
Section of reinforced slab in loading dock. East most section of loading dock drive...2" foam, #3 epoxy coated rebar and wirsbo piping for heated slab. Approved for concrete placement.

Structural Inspection Partial Pass 05/05/2017
Corrections:


Miscellaneous/Other
Comment Only
05/05/2017
Wall sections located behind the retaining wall. Approved for concrete placement.

Structural Inspection Partial Pass 05/15/2017
Corrections:


Miscellaneous/Other
Comment Only
05/15/2017
All rebar reinforcement in the heated driveway slab is approved. Verbal to contractor to go through and cut any long ends along edges that will not have full encasement coverage of concrete...cut ends should be repainted with epoxy paint. This slab will be poured in sections.

Footing Inspection Partial Pass 06/14/2017
Corrections:


Miscellaneous/Other
Comment Only
06/14/2017
Footing for the retaining wall at the base of the existing old loading dock approved for concrete placement.

Structural Inspection Partial Pass 06/15/2017
Corrections:


Miscellaneous/Other
Comment Only
06/15/2017
Section of wall on top of footing placed on 6/14/17 at old loading dock. Ok to place concrete to wall forms.

Structural Inspection Partial Pass 06/19/2017
Corrections:


Miscellaneous/Other
Comment Only
06/19/2017
Small section of retaining wall alongside the existing old loading dock. Approved for concrete placement.

Footing Inspection Partial Pass 06/23/2017
Corrections:


Miscellaneous/Other
Comment Only
06/23/2017
Retaining wall footing for the enclosure of the old ramp. Approved

Structural Inspection Partial Pass 06/26/2017
Corrections:


Miscellaneous/Other
Comment Only
06/26/2017
End Wall section at old ramp location. Tie in's to existing retaing walls, rebar mats... approved for concrete placement.

Structural Inspection Partial Pass 6/30/2017 (12:30 - 2:30) 6/30/2017 06/30/2017
Corrections:


Miscellaneous/Other
Comment Only
06/30/2017
West drive lane of executive ramp, rebar and in slab heat piping approved, air test holding at 108 psi on gauge. Approved for concrete placement.

Structural Inspection Passed 10/11/2017
Corrections:


Miscellaneous/Other
Comment Only
10/11/2017
All structural work is completed per the scope of this permit. Approved to close out this permit with any remaining inspection results for bathrooms and the Mechanical room or any other locations inspections are needed, will be referred to permit #201700913.

Building Final Inspection Passed 11/22/2017
Corrections:


Miscellaneous/Other
Comment Only
11/22/2017
All structural work completed, see permit PRBD201700913 for other inspection results.

Miscellaneous/Other
Comment Only
11/22/2017
Correction... see permit PRBD 2017000913 for other inspection results