PRST202000821
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed | 5/4/2020 (12:30 - 2:30) | 5/4/2020 (PM) | 05/04/2020 |
Corrections:
Miscellaneous/Other
Comment Only
05/04/2020
Progress framing inspection includes sheet rock of rated shaft, nailing patterns of exterior shear walls, progress on two hour separation wall. All approved.
|
||||
Framing Inspection | Passed w/ Conditions | 5/8/2020 (12:30 - 2:30) | 5/11/2020 (PM) | 05/11/2020 |
Corrections:
Miscellaneous/Other
Comment Only
05/11/2020
Note, progress framing inspection of rated grease shaft and trash shaft at first and second floors. Address comments as discussed in field to be inspected on follow up inspection.
|
||||
Framing Inspection | Passed | 5/13/2020 (12:30 - 2:30) | 5/13/2020 (PM) | 05/13/2020 |
Corrections:
Miscellaneous/Other
Comment Only
05/13/2020
Corrections completed as required for rated trash and grease shaft on second floor.
|
||||
Progress Inspection | Passed | 6/10/2020 (12:30 - 2:30) | 6/10/2020 (PM) | 06/10/2020 |
Corrections:
Miscellaneous/Other
Comment Only
06/10/2020
Progress inspection of framing on third floor OK.
|
||||
Progress Inspection | Passed | 6/15/2020 (12:30 - 2:30) | 6/15/2020 (PM) | 06/15/2020 |
Corrections:
Miscellaneous/Other
Comment Only
06/15/2020
Pre-framing progress inspection of all floors to verify to our rated shaft integrity.
|
||||
Progress Inspection | Passed | 6/24/2020 (12:30 - 2:30) | 6/24/2020 (PM) | 06/24/2020 |
Corrections:
Miscellaneous/Other
Comment Only
06/24/2020
Progress inspection of fourth floor framing OK. Progress inspection of roof insulation and membrane approved.
|
||||
Building Final Inspection | Passed | 04/02/2021 |