PRST202406416
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Building Final Inspection | Pending | |||
Progress Inspection | Pending | |||
Framing Inspection | Passed | 1/24/2025 (8:00 - 10:00) | 1/24/2025 (AM) | 01/24/2025 |
Corrections:
Miscellaneous/Other
Comment Only
01/24/2025
Remainder of second floor framing of kitchen area and east shft and south shaft of 3rd and 4th levels... approved, pending a recheck of firestops at through floor electrical feed piping on second floor.
|
||||
Progress Inspection | Passed | 1/29/2025 (8:00 - 10:00) | 1/29/2025 (AM) | 01/29/2025 |
Corrections:
Miscellaneous/Other
Comment Only
01/29/2025
Fire stops at electrical through floor feeds of 2nd floor approved
Poly and reinforcement for Slab on grade from grids B to E, lines 1 to 6... approved
|
||||
Framing Inspection | Passed | 6/10/2025 (10:00 - 12:00) | 6/10/2025 (AM) | 06/10/2025 |
Corrections:
Miscellaneous/Other
Comment Only
06/10/2025
Framing of vestibule and misc framing in skyway... approved
Overall walk of building .... work is still in process, no code issues found that needs to be addressed at this time.
|