Permit Application Status

PRSTSTST201700455


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRSTSTST201700455
Structural
Finaled
BLOOMINGTON CENTRAL STATION LLC
New
Not Required
New 8 level parking ramp, structual precast to include columns, inverted tee-beams, double tees, and strucutural sprandrel panels.
02/10/2017
02/14/2017
05/01/2018

Locations

Permits

Permit Number: PRSTSTST201700455

Building
Finaled
02/14/2017
05/01/2018

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Progress Inspection Partial Pass 3/1/2017 (12:30 - 2:30) 3/1/2017 03/01/2017
Corrections:


See Document Markups
Comment Only
03/01/2017
See Document Markups Pad footings on grid "F" lines 8 & 10 approved for concrete placement.

Structural Inspection Partial Pass 3/3/2017 (12:30 - 2:30) 3/3/2017 03/03/2017
Corrections:


See Document Markups
Comment Only
03/03/2017
See Document Markups Running footing between lines 8 & 9 on grid "F", pad footings on lines 4,5,6,& 7 on grid "F", strip footing on line 10 between "E & D" and pad footings on grid "D" lines 8-10. Approved for concrete placement.

Structural Inspection Partial Pass 3/6/2017 (12:30 - 2:30) 3/6/2017 03/06/2017
This inspection was added because Jon and contractor wanted it on the schedule ... other inspection pending. ajacobson 03/02/2017 2:43 PM
Corrections:


See Document Markups
Comment Only
03/06/2017
See Document Markups: pad footings at line "C" grids 8 & 10. Infill pads along line "E" grids 4-10. Approved for concrete placement.

Structural Inspection Partial Pass 3/8/2017 (12:30 - 2:30) 3/8/2017 03/08/2017
Corrections:


Miscellaneous/Other
Comment Only
03/08/2017
Shear wall with column on grid line 10 between "E &D". Section of footin "WF8-0" on grid line "D" 5-10. Approved.

Structural Inspection Partial Pass 3/10/2017 (12:30 - 2:30) 3/10/2017 03/10/2017
Corrections:


Miscellaneous/Other
Comment Only
03/10/2017
Strip footings on grid "D" fill in between pads. Pad footings on grid "E" @ lines 1-2&3. Shear wall on grid 10 D to C with column on C -10 pad. Approved for concrete. Frost blankets on site for protection from freeze due to drop in temperature.

Structural Inspection Partial Pass 3/13/2017 (12:30 - 2:30) 3/13/2017 03/13/2017
Corrections:


Miscellaneous/Other
Comment Only
03/13/2017
Wall section between "E&D" on grid 10. Wall section on grid "E" at 7-8. Approved for concrete placement.

Structural Inspection Partial Pass 3/15/2017 (12:30 - 2:30) 3/15/2017 03/15/2017
Corrections:


Miscellaneous/Other
Comment Only
03/15/2017
Infill footing pads and wall sections on line"E" from 2-5. Approved for concrete placement. Footing pad on line"D" at grid 3... approved for concrete placement. Wall section on line "D" approx grid 5-8, approved.

Structural Inspection Partial Pass 3/16/2017 (12:30 - 2:30) 3/16/2017 03/16/2017
Corrections:


Miscellaneous/Other
Comment Only
03/16/2017
Wall section on grid "E" 5-6, grid "D" 5-8, and footing grid "C"4.5-8. Approved for concrete placement.

Structural Inspection Partial Pass 3/17/2017 (12:30 - 2:30) 3/17/2017 03/17/2017
Corrections:


Miscellaneous/Other
Comment Only
03/17/2017
Wall footing at grid 7 "E-D". Wall footing at grid "C" 6-4. Strip footing on grid 1 "D-E". Section of wall on grid "E" 3-4. These areas are approved for concrete placement.

Structural Inspection Partial Pass 3/20/2017 (12:30 - 2:30) 3/20/2017 03/20/2017
Corrections:


Miscellaneous/Other
Comment Only
03/20/2017
Wall section at grid 7, "E-D". Wall footing on grid "D", 3-4. Wall section on grid "D"4-6.

Structural Inspection Partial Pass 3/21/2017 (12:30 - 2:30) 03/21/2017
Corrections:


Miscellaneous/Other
Comment Only
03/21/2017
Wall section on grid 1, "E-D". Approx. 1/3 install of waterproofing and foam to wallon grid line "E". Pad footing on grid line 1, line "C". Wall rebar on grid "C" lines 4-8 installed.

Structural Inspection Partial Pass 03/22/2017
Corrections:


Miscellaneous/Other
Comment Only
03/22/2017
Pad footings at grid line1"D & B" grid lines. 32ft of running footing attached to pad footin at line 1 grid "C" running N & S of that pad footing. Rebar at wall on Grid "C" is formed up for pour, clearances have been addressed. Verticals for wall on the pads at grid 1 are on site and will be put in, verified with Forman and A.T.I special inspector, to install and verify, since they were still working on bracing forms when pad was inspected.

Structural Inspection Partial Pass 03/24/2017
Corrections:


Miscellaneous/Other
Comment Only
03/24/2017
Clearances checked at wall section pour on grid line"C" approved.8-6.5. Running footing adjoining pads on grid line 1 at pads "D", & "B". Wall section on grid line 1 halfway between "D-C" & "B-C". Column at pad on line 1-C. Footing pad on grid line "A" 1-2, & pad at grid 3.

Structural Inspection Partial Pass 3/27/2017 (12:30 - 2:30) 3/27/2017 03/27/2017
Corrections:


Miscellaneous/Other
Comment Only
03/27/2017
Wall section on grid line 1, at line E.5 to D.5. Approved for concrete

Structural Inspection Partial Pass 03/28/2017
Corrections:


Miscellaneous/Other
Comment Only
03/28/2017
Wall section on grid 1, from C-B. Strip footing from B.5-"A"footing pad. Wall section on grid "C" clearances ok. Waterproofing and draintile at section on grid 10 wall, and grid "E" wall approved.

Structural Inspection Partial Pass 03/29/2017
Corrections:


Miscellaneous/Other
Comment Only
03/29/2017
Wall section at grid 1, B.5-C.5. Footing at grid 1 - 2 all corner section pads at line "A". Grid 4, footing between lines "C" to "D". Approved for concrete. Contractor is finishing install of the section at A-1-2 , all rebar on site, he will verify full completion.

Structural Inspection Partial Pass 3/30/2017 (12:30 - 2:30) 3/30/2017 03/30/2017
Corrections:


Miscellaneous/Other
Comment Only
03/30/2017
pad footings on grid line "A" line 8, & 9/10. Footing bars to connect pads not installed and will have to be epoxied in. Footing pads on grid line3, lines "B" & "C". Approved for concrete. Rebar for wall section with column at corner of grid lines "A" & "1" approved. Forming for pour on 3/31.

Structural Inspection Partial Pass 4/3/2017 (12:30 - 2:30) 4/3/2017 04/03/2017
Corrections:


Miscellaneous/Other
Comment Only
04/03/2017
Small strip footing connection to pad at grid line "C" at line 3.5. Wall section with columns at grid line 1-2 on line "A". ( corner wall section). Footing strip on grid line a from grid lines 3-7. Approved for concrete placement.

Structural Inspection Partial Pass 04/04/2017
Corrections:


Miscellaneous/Other
Comment Only
04/04/2017
Top of wall section at grid "C" from 5-4.5 approx. remainder of wall footing on line "A", 7- 9. Pad footing at line "B", grid 5. Soil corrections done at this footing . Approved for concrete placement.

Structural Inspection Partial Pass 04/05/2017
Corrections:


Miscellaneous/Other
Comment Only
04/05/2017
Footing pad at grid "B", line 6. Soil correction also done at this location. Remainder of wall section on grid "C" , from 3-3.5. Wall section between grid "C-D" on line 4. Approved for concrete placement.

Structural Inspection Partial Pass 4/10/2017 (12:30 - 2:30) 4/10/2017 04/07/2017
Corrections:


Miscellaneous/Other
Comment Only
04/07/2017
Poured wall section at grid "A" lines 3-4.5. Wall section at grid 2 in that NW corner.

Structural Inspection Partial Pass 04/10/2017
Corrections:


Miscellaneous/Other
Comment Only
04/10/2017
Wall section on line "A" at approximately up to line 7. Approved for concrete. Strip footing at line "A"to "A.75" on grid 10,(elevator location) approved for concrete.

Structural Inspection Partial Pass 04/11/2017
Corrections:


Miscellaneous/Other
Comment Only
04/11/2017
Pad footings on line"B" at grids 7 & 8, soil corrections completed and rebar approved as per plan. Wall section on loading ne "A" at grids 6.75- 7.5. Approved for concrete placement.

Structural Inspection Partial Pass 4/13/2017 04/13/2017
Corrections:


Miscellaneous/Other
Comment Only
04/13/2017
Rebar for wall section on grid "A" from 7.5-10, and line 10-10.5. Approved for concrete. De-watering in process at elevator pad location grid "B - C".

Structural Inspection Not Ready 4/18/2017 (12:30 - 2:30) 4/18/2017 04/18/2017
Corrections:


Miscellaneous/Other
Comment Only
04/18/2017
Inspection canceled due to weather

Structural Inspection Not Ready 4/19/2017 (12:30 - 2:30) 4/19/2017 04/19/2017
Corrections:


Miscellaneous/Other
Comment Only
04/19/2017
Canceled due to rain

Structural Inspection Partial Pass 04/20/2017
Corrections:


Miscellaneous/Other
Comment Only
04/20/2017
Elevator pad footing has waterproof membrane installed as shown on the prints. 3 floor drains, 4" diameter installed. Rebar is as per designed plans. Located at B.2.5 to line C. This section is bullheaded off for concrete placement today 4/20/17.

Structural Inspection Partial Pass 4/21/2017 (12:30 - 2:30) 4/21/2017 04/21/2017
Corrections:


Miscellaneous/Other
Comment Only
04/21/2017
Footing pad at line 9-10 on grid "B" and adjoins pad on line 10 at grid "B.2" location. Approved for concrete placement.

Structural Inspection Partial Pass 4/27/2017 (12:30 - 2:30) 4/27/2017 04/27/2017
Corrections:


Miscellaneous/Other
Comment Only
04/27/2017
Footings at Line " A" at the infills to the pads approx A.5-C. Wall sections from B.2- C at elevator section of footing. Dowels to be installed ar the strip footings, AET inspector to verify installation.

Structural Inspection Partial Pass 4/28/2017 (12:30 - 2:30) 4/28/2017 04/28/2017
Corrections:


Miscellaneous/Other
Comment Only
04/28/2017
Wall section on line 10 at C.5. Half wall between B.2-C. Wall section on line 10 at A.75-B. Approved for concrete placement.

Structural Inspection Partial Pass 5/2/2017 (12:30 - 2:30) 5/2/2017 05/02/2017
Corrections:


Miscellaneous/Other
Comment Only
05/02/2017
Formed wall section on line 10 at A.5. Short wall section at approx. B.3 , and wall section at line C. Approved for concrete placement

Structural Inspection Partial Pass 5/4/2017 (12:30 - 2:30) 5/4/2017 05/04/2017
Corrections:


Miscellaneous/Other
Comment Only
05/04/2017
Short wall section between grids B.2-C on line 10. Wall section on line 10 B-B.2. Approved for concrete placement.

Structural Inspection Partial Pass 5/5/2017 (12:30 - 2:30) 5/5/2017 05/05/2017
Corrections:


Miscellaneous/Other
Comment Only
05/05/2017
Last wall section at the line 10 elevator section. Approved for concrete placement

Structural Inspection Partial Pass 7/13/2017 (8:00 - 10:00) 7/13/2017 07/13/2017
Corrections:


Miscellaneous/Other
Comment Only
07/13/2017
2 footings for signs located between main building and ramp within property. Approved for concrete.

Structural Inspection Not Ready 7/14/2017 (12:30 - 2:30) 7/14/2017 07/14/2017
Corrections:


Miscellaneous/Other
Comment Only
07/14/2017
Contractor canceled inspection.

Structural Inspection Partial Pass 08/01/2017
Corrections:


Miscellaneous/Other
Comment Only
08/01/2017
Viewed shaft wall framing at top of elevator front/ parapet. Approved to 1st layer wall. Inspection of first layer needed prior to second layer covering.

Structural Inspection Partial Pass 8/8/2017 (12:30 - 2:30) 8/8/2017 08/08/2017
Corrections:


Miscellaneous/Other
Comment Only
08/08/2017
First layer gypsum board on the interior shaft wall divider between Mech. Room and elevator. Approved to cover.

Structural Inspection Passed 9/5/2017 (12:30 - 2:30) 9/5/2017 09/05/2017
Exterior concrete stoop footings per plan. Exterior poured walls per plan tomorrow, with hook bars top of wall for stoop concrete surface. Stoop concrete mix must have 5-7 percent air per IBC 2015, CONCRETE EXPOSED TO MOISTURE AND FREEZING. 3 STOOP LOCATIONS - SOUTH EAST, NORTH EAST, AND NORTH WEST.
Structural Inspection Partial Pass 9/13/2017 (10:00 - 12:00) 9/13/2017 09/13/2017
Corrections:


Miscellaneous/Other
Comment Only
09/13/2017
Framing for lobby wall front on floors 1-6 of ramp , approved to cover.

Building Final Inspection Passed 10/11/2017
Corrections:


Miscellaneous/Other
Comment Only
10/11/2017
All the structural elements to the building of the ramp, and for the scope of this permit are completed. Refer to permit #201700917 for remaining inspection results that will follow with completion of the parking ramp.

Structural Inspection Partial Pass 11/1/2017 (12:30 - 2:30) 11/1/2017 11/01/2017
Corrections:


Miscellaneous/Other
Comment Only
10/11/2017
Floors 3-6 approved for 1st layer gypsum, floors 1,2,7 approved to install first layer gypsum.

Structural Inspection Partial Pass 11/2/2017 (12:30 - 2:30) 11/2/2017 11/02/2017
Corrections:


Miscellaneous/Other
Comment Only
11/02/2017
Elevator lobbies: floors lower level, one, two, and seven, first layer of gypsum and fire caulking approved. All elevator lobbies are approved for second layer of gypsum, fire caulking is complete at all Levels and at all penetrations of shaft walls.