PRTP202111972
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Fire Inspection Final | Pending | |||
| Tank Support Inspection | Pending | |||
| Fire Inspection Final | Partial Pass | 10/27/2021 (10:00 - 12:00) | 10/27/2021 (PM) | 10/27/2021 |
| Waiting for more soil sample results from the 3rd party firm. Be sure to follow all osha requirements for trench operations at all times. No exceptions!! | ||||
| Tank Air Test Inspection | Partial Pass | 10/27/2021 (10:00 - 12:00) | 10/27/2021 (AM) | 10/27/2021 |
| Hook up occurs in a couple of weeks. Advised to contact COB to see if a mechanical permit is required. | ||||
| Tank Support Inspection | Partial Pass | 10/27/2021 (10:00 - 12:00) | 10/27/2021 (AM) | 10/27/2021 |
| Tank Air Test Inspection | Passed | 11/5/2021 (12:30 - 2:30) | 11/5/2021 (PM) | 11/08/2021 |