Permit Application Status

PRST201711841


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRST201711841
Structural
Finaled
FELCOR/CSS HOLDINGS SPE
Alteration/Remodel
Not Required
Structural permit for Embassy Suites Hotel. Install concrete piers and footings for walls and posts. Install trenches for underground waste, water, and electrical. Install concrete for raised platform in atrium. Separate building permit will be issued as well.
12/13/2017
12/15/2017
02/24/2019

Locations

Permits

Permit Number: PRST201711841

Building
Finaled
12/15/2017
02/24/2019

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Footing Inspection Partial Pass 1/10/2018 (8:00 - 10:00) 1/10/2018 01/10/2018
Corrections:


Miscellaneous/Other
Comment Only
01/10/2018
Footings all marked on plans as to what was viewed and can be poured. Approved for concrete.

Footing Inspection Partial Pass 1/31/2018 (8:00 - 10:00) 1/31/2018 01/31/2018
Corrections:


Miscellaneous/Other
Comment Only
01/31/2018
Remaining footings for trellis approved for concrete. This inspection completes all the footings that are needed for inspection.

Footing Inspection Partial Pass 2/16/2018 (8:00 - 10:00) 2/16/2018 02/16/2018
Corrections:


Miscellaneous/Other
Comment Only
02/16/2018
Raised floor detail with rebar #4 - 9” spacing each way over foam infill. Approved for concrete placement. Ramp slope to be checked by contractor and verified by inspector.

Progress Inspection Partial Pass 2/26/2018 (10:00 - 12:00) 2/26/2018 02/26/2018
Per Jon, progress inspection may still be required and not ready for final. ajacobson 01/31/2018 9:12 AM Contractor indicates not required - wanted final inspection on 1/31/2018. ajacobson 01/29/2018 11:42 AM
Corrections:


Miscellaneous/Other
Comment Only
02/26/2018
Walls in bell mans room, west lobby feature wall, office, fitness center, azalea room closet, public and pool room bathrooms.

Framing Inspection Partial Pass 3/14/2018 (8:00 - 10:00) 3/14/2018 03/14/2018
Corrections:


Miscellaneous/Other
Comment Only
03/14/2018
Wall framing in atrium area approved to cover. Ceilings in bathrooms, pool bath and shower, market area, elevator lobbies. Approved to cover pending fire sprinkler inspections.

Building Final Inspection Passed 08/28/2018
Corrections:


Miscellaneous/Other
Comment Only
08/28/2018
Structural permit only, this scope of work is completed . See the permit issued for the remainder of the buildout for other inspections. This permit is approved to close and final.