Planning Application Status

PL202100255


Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PL202100255
Seagate Expansion - 7801 Computer Ave S and 7850 Nord Ave S - Major Revision to PDP/FDP
Development Application
Preliminary Development Plan
Final Development Plan
File Closed
12/07/2021
SEAGATE TECHNOLOGY INC
Major Revision to Preliminary and Final Development Plans for a two-story, approximately 81,000 square-foot building addition to an existing technology campus.

Locations

Application Types

Preliminary Development Plan

Planning Commission & Council
Approved w/Conditions

Final Development Plan

Planning Commission & Council
Approved

Fees

There are no fees for this planning application, or you are not authorized to view them.

Deposits & Bonds

There are no deposits or bonds for this planning application.

Hearings

Title Location Date Time
Planning Commission, 2022-01-27, 06:00 PM City Hall Council Chambers 01/27/2022 6:00 PM
Recommendation to Council
Continued
Planning Commission, 2022-02-03, 06:00 PM City Hall Council Chambers 02/03/2022 6:00 PM
Recommendation to Council
Recommend Approval
Council, 2022-02-14, 07:00 PM City Hall Council Chambers 02/14/2022 7:00 PM
Final Action

Inspections

There are no inspections for this planning application, or you are not authorized to view them.

Documents & Images

Date Uploaded File Type Name
12/09/2021 Map Notification Labels and Map
12/10/2021 Receipt Receipt of Payment
12/15/2021 Letter Complete Application Notice
12/27/2021 Form Development Application
12/30/2021 Activity Document DRC Meeting Minutes and Comment Summary
01/11/2022 Letter Agency Action Deadline Extension
02/02/2022 Notices Public Hearing Notices
02/16/2022 Report Staff Report and Conditions
02/16/2022 Email MPCA Determination for No Sanitary Permit
02/16/2022 Letter Decision Notice
02/16/2022 Form Tier 2 TDM Checklist
02/16/2022 Plans Existing Conditions Survey
02/16/2022 Letter Project Description and Review Responses
02/17/2022 Plans Parking Calculations
02/17/2022 Plans Plans Arch Reviewed
02/23/2022 Report Geotech Report
03/22/2022 Letter MDH review response
03/22/2022 Plans Building Rendering
03/25/2022 Plans Building Material Calcs and Info
03/30/2022 Plans Approved Landscaping 7850 Nord
04/12/2022 Construction Management Plan
04/21/2022 Permit NMCWD Permit Approval Letter
04/21/2022 Permit NPDES Permit
04/21/2022 Plans Stormwater Mangement Report Approved
05/03/2022 Agreement Proof of Parking Agreement
05/03/2022 Agreement Site Development Agreement Recorded
05/31/2022 Report Staff Memo Parking Update
06/01/2022 Plans Approved Civil 7850 Nord
06/09/2022 Email Mechanical Screening Information
06/13/2022 Plans Approved Lighting 7950 Nord
08/01/2022 Agreement Right-of-Way Use Agreement Recorded