PRFS202504584
|
Fire Suppression System
|
Alteration/Repair/Replace
|
Permit(s) Issued
|
05/14/2025
|
|
:
Fire Suppression System
:
Add/relocate pendants to uprights in renovation area.
|
PREL202502643
|
Electrical
|
Alteration/Repair/Replace
|
Permit(s) Issued
|
03/17/2025
|
|
:
Electrical
:
JOB 50060 HEALTH PARTNERS / LAKEVIEW HOSPITAL MOCK-UP PROJECT
|
PREL202500175
|
Electrical
|
Alteration/Repair/Replace
|
Permit(s) Issued
|
01/07/2025
|
|
:
Electrical
:
JOB 25010290 HEALTH PARTNERS COOLING UNIT REPLACEMENT
|
PRBD202500037
|
Building
|
Alteration/Repair/Replace
|
Permit(s) Issued
|
04/24/2025
|
|
:
Building
:
Demolition of walls in space with the intent of maintaining a vanilla shell. The space will be used for mockup setups of future designs, which will change based on different needs. The space will serve as a design mockup area.
|
PREL202416046
|
Electrical
|
Alteration/Repair/Replace
|
Permit(s) Issued
|
12/11/2024
|
|
:
Electrical
:
JOB 24120421HEALTHPARTNERS 2170 INSTALL 12 RECEPTACLES IN CONFERENCE ROOMS
|
PRPL202415180
|
Plumbing
|
Alteration/Repair/Replace
|
Expired
|
11/15/2024
|
|
:
Plumbing
:
Replace 10 roof drains to allow for roofing project.
|
PRMH202414269
|
Mechanical/HVAC
|
Alteration/Repair/Replace
|
Expired
|
10/28/2024
|
|
:
Mechanical
:
Remove HVAC equipment to accommodate reroof project .
|
PREL202411855
|
Electrical
|
Alteration/Repair/Replace
|
Finaled
|
09/10/2024
|
|
:
Electrical
:
JOB 820328 HP 8170 ROOF REPLACEMENT - DISCONNECT AND RECONNECT MECHANICAL EQUIPMENT FOR ROOF REPLACEMENT - FINAL INSPECTION
|
PRTC202410240
|
Tent/Canopy
|
Other
|
Finaled
|
08/08/2024
|
|
:
Tent/Canopy
:
Canopy installation 30'x15' over a stage for City of Bloomington event on 8/17 2pm-9pm
|
PRCRF202407287
|
Roof, Commercial
|
Alteration/Repair/Replace
|
Permit(s) Issued
|
08/27/2024
|
|
:
Roofing
:
Removal and replacement of existing roofing system, three buildings. MEP related work, including removal and reinstallation of the lightning protection system.
|
PRMH202404908
|
Mechanical/HVAC
|
Alteration/Repair/Replace
|
Expired
|
04/23/2024
|
|
:
Mechanical
:
Job# 88042
9th Floor - Replace three(3) existing CRAC units with ne Liebert units.
|
PREL202402619
|
Electrical
|
Alteration/Repair/Replace
|
Finaled
|
03/06/2024
|
|
:
Electrical
:
JOB 24010013 HP MRCC RELOCATION - ADD (6) NEW SYSTEMS FURNITURE CONNECTIONS, ADD (2) NEW POWER POLES, NEW 2X2 AND 2X4 LED LIGHTING WITH DIMMING. NEW 60A, 208V PANEL TO SERVICE THE SPACE.
|
PREL202402007
|
Electrical
|
Alteration/Repair/Replace
|
Expired
|
02/21/2024
|
|
:
Electrical
:
JOB 24020994 HP - DISCONNECTING A COOLING UNIT AND EXTENDING CIRCUIT TO NEW LOCATION AND RECONNECTING
|
PRFS202215691
|
Fire Suppression System
|
Alteration/Repair/Replace
|
Expired
|
01/03/2023
|
|
:
Fire Suppression System
:
remove and relocate (3) sprinklers that are too close together. Also add (3) sprinklers to complete coverage on the 7th floor north.
|
PREL202204305
|
Electrical
|
Alteration/Repair/Replace
|
Expired
|
04/25/2022
|
|
:
Electrical
:
JOB 22040077 HP ADD 5 RECEPTACLES FOR MONITORS IN CONFERENCE ROOMS (LAKE OF THE WOODS) SUPERIOR, MINNESOTA, ST CROIX, MISSISSIPPI).
|
PREL202204302
|
Electrical
|
Alteration/Repair/Replace
|
Expired
|
04/22/2022
|
|
:
Electrical
:
ADD (35) TOTAL 120V 20A DEDICATED NORMAL POWER RECEPTACLES TO NETWORK CLOSETS. LIST ATTACHED. NEW RECEPTACLES WILL BE FED FROM ADJACENT ELECTRICAL ROOM THAT SHARES A WALL WITH THE NETWORK CLOSET.
|
PREL202204219
|
Electrical
|
Alteration/Repair/Replace
|
Finaled
|
04/25/2022
|
|
:
Electrical
:
JOB 21070837 HEALTH PARTNERS 8170 LIGHT POLES - 1 FOR 1 SWAP OF 5 LIGHT POLES - DIRECTIONAL BORING CONDUIT AND PULLING NEW WIRE FROM AN ADJACENT POLE TO ONE OF THE 5 POLES TO REPLACE EXISTING FEED.
|
PRPL202107924
|
Plumbing
|
Alteration/Repair/Replace
|
Finaled
|
07/21/2021
|
|
:
Plumbing
:
Backflow preventer replacement- commercial
|
PRFS202107452
|
Fire Suppression System
|
Alteration/Repair/Replace
|
Finaled
|
09/02/2021
|
|
:
Fire Suppression System
:
ADD/RELOCATE SPRINKLER HEADS FOR NEW ROOM AND GRID LAYOUT
|
PREL202107005
|
Electrical
|
Alteration/Repair/Replace
|
Expired
|
06/14/2021
|
|
:
Electrical
:
Fire alarm wiring for 12th Fl remodel at Bloomington Corporate Center 12048
|
PRAL202107004
|
Fire Alarm
|
Other
|
Finaled
|
06/09/2021
|
|
:
Fire Alarm
:
Add and relocate existing speaker/strobes & strobes as need for 12th Fl remodel at Bloomington Corporate Center 12048
|
PRMH202106636
|
Mechanical/HVAC
|
Alteration/Repair/Replace
|
Finaled
|
06/08/2021
|
|
:
Mechanical
:
Modify duct distribution for new office layout.
|
PREL202106566
|
Electrical
|
Alteration/Repair/Replace
|
Finaled
|
06/01/2021
|
|
:
Electrical
:
JOB 84020
HEALTHPARTNERS 12TH LEVEL POWER AND SYSTEMS - REMODEL OF THE 12TH FLOOR - POWER FOR NEW SYSTEMS FURNTIURE, POWER FOR NEW OFFICES AND CONFERENCE ROOMS, RELOCATE LIGHTING THROUGHOUT - NO NEW DISTRIBUTION
|
PRPL202106285
|
Plumbing
|
Alteration/Repair/Replace
|
Finaled
|
05/26/2021
|
|
:
Plumbing
:
install break area sink and dishwasher
|
PRBD202106211
|
Building
|
Alteration/Repair/Replace
|
Finaled
|
06/08/2021
|
|
:
Building
:
Build out of offices and added finishes
|
PRGR202104687
|
Grading
|
Alteration/Repair/Replace
|
Expired
|
06/09/2021
|
|
:
Grading
:
Removal of a 200 foot by 30 foot section of private concrete roadway, to be replaced with bituminous paving. Replacement of 17 cracked sidewalk panels, and adjacent curb/gutter to road.
|
PREL202103790
|
Electrical
|
Alteration/Repair/Replace
|
Expired
|
04/09/2021
|
|
:
Electrical
:
JOB 21040158 HP PANEL ADDITION - ADD SWITCH TO EXISTING MCC - RUN PRMARY FEED TO 75KVA TRANSFROMER - RUN SECONDARY FEED TO 208V PANEL
|
PREL202103109
|
Electrical
|
Alteration/Repair/Replace
|
Expired
|
03/31/2021
|
|
:
Electrical
:
JOB 21030843 BLOOMINGTON CENTRAL STATION RAMP SECURITY
PROVIDE AND INSTALL DEDICATED DUPLEX RECEPTACLE IN ELECTRICAL ROOM
|
PREL202013818
|
Electrical
|
Alteration/Repair/Replace
|
Finaled
|
11/10/2020
|
|
:
Electrical
:
JOB 20110163 HP COVID TESTING AREA - Adding (2) lights
Adding (2) exit signs - Adding (4) 3.2kw infrared heaters with 20-amp 480-volt home runs. Adding associated breakers to existing panel.
|
PRBD202013613
|
Building
|
Other
|
Finaled
|
11/19/2020
|
|
:
Building
:
Temporary Enclosure for drive-up COVID testing
|
PRBD202008775
|
Building
|
Alteration/Repair/Replace
|
Expired
|
08/18/2020
|
|
:
Building
:
Building 12th floor, approximately 25,000 sf. Demo all existing walls (private offices and meeting rooms), remove carpet, grind floors smooth, and remove existing ceiling tile. Ceiling grid to remain.
|
PRCRF202003341
|
Roof, Commercial
|
Alteration/Repair/Replace
|
Expired
|
04/16/2020
|
|
:
Roofing
:
Complete tear off and replacement of an existing flat roof
|
PRTC202001410
|
Tent/Canopy
|
Other
|
Expired
|
02/14/2020
|
|
:
Tent/Canopy
:
SEIU Healthcare Members at HealthPartners are conducting an unfair labor practices strike at HealthPartners corporate site in Bloomington. A small popup tent will be used during the event. The members will be holding picket signs, singing and saying chants. There will be rallies where words are spoken over amplification equipment. Music may be played over speakers also. The event runs daily from 7:00 AM - 7:00 PM from 2/19/2020 to 2/25/2020.
|
PRROWS202001217
|
ROW Small Cell
|
N/A
|
Finaled
|
02/08/2020
|
|
:
Right-of-Way
:
New small cell on Xcel owned pole. Permit issued in 2019.
|
PREL201914741
|
Electrical
|
Other
|
Finaled
|
12/16/2019
|
|
:
Electrical
:
Cell tower - new service and 2 circuits on pole
On light pole in right of way on north side of old Shakopee Rd
|
PRMH201911740
|
Mechanical/HVAC
|
Alteration/Repair/Replace
|
Finaled
|
10/07/2019
|
|
:
Mechanical
:
Relocate supply diffusers and round supply runouts for new wall locations
|
PRFS201910746
|
Fire Suppression System
|
Alteration/Repair/Replace
|
Expired
|
09/17/2019
|
|
:
Fire Suppression System
:
RELOCATE 8 HEADS FOR TENANT REMODEL
|
PREL201908430
|
Electrical
|
Alteration/Repair/Replace
|
Finaled
|
07/29/2019
|
|
:
Electrical
:
Wiring for fire alarm system for the remodel of 9th Floor West at Bloomington Corporate Center 11486
|
PRAL201908428
|
Fire Alarm
|
Alteration/Repair/Replace
|
Finaled
|
07/29/2019
|
|
:
Fire Alarm
:
Relocating existing speaker/strobes and add to strobes as needed for the remodel of 9th Floor West at Bloomington Corporate Center 11486
|
PRPL201908417
|
Plumbing
|
Alteration/Repair/Replace
|
Expired
|
07/30/2019
|
|
:
Plumbing
:
Replace drinking foutain with break room sink.
|
PREL201907866
|
Electrical
|
Other
|
Finaled
|
07/16/2019
|
|
:
Electrical
:
JOB 83719 HEALTH PARTNERS REMODEL OF 9TH FLOOR WEST OPEN OFFICE. INCLUDES NEW SYSTEMS, FURNITURE AND POWER FEEDS.
|
PRBD201905425
|
Building
|
Alteration/Repair/Replace
|
Finaled
|
06/11/2019
|
|
:
Building
:
Remodel 9th Floor West
|
PRFS201901731
|
Fire Suppression System
|
Other
|
Finaled
|
03/04/2019
|
|
:
Fire Suppression System
:
Convert existing loading dock wet sprinkler system to a dry system.
|
PREHP201901154
|
Environmental Health Plan
|
Other
|
Permit(s) Issued
|
02/22/2019
|
|
:
Environmental Health Plan
:
Main cafeteria island hood action station upgrade.
|
PRPL201805113
|
Plumbing
|
Repair/Replace
|
Finaled
|
05/30/2018
|
|
:
Plumbing
:
Health Partners- RPZ's - 6 removed, one existing and 2 new installations.
|
PREL201712026
|
Electrical
|
Alteration/Remodel
|
Finaled
|
12/20/2017
|
|
:
Electrical
:
Job# 9015022 Provide temporary wiring for 60kW and 30kW temporary portable generators for Super Bowl event.
|
PRFS201711799
|
Fire Suppression System
|
Alteration/Remodel
|
Finaled
|
01/02/2018
|
|
:
Fire Suppression System
:
Add/relocate or plug 2-8 sprinkler heads on each floor. See scanned plans attached.
|
PRPL201710115
|
Plumbing
|
Alteration/Remodel
|
Finaled
|
10/23/2017
|
|
:
Plumbing
:
Install 3 new RPZ's. Serial #61473 located in Water/Sprinkler Riser Room Lower Level. Serial #27057 located in Water/Sprinkler Riser Room Lower Level. Serial #192435 located in Water/Sprinkler Riser Room Lower Level.
|
PREL201709712
|
Electrical
|
Alteration/Remodel
|
Finaled
|
10/12/2017
|
|
:
Electrical
:
Electrical for new monument signs at BCS Health Partners. Job #81333 Phase 101.
|
PREL201708503
|
Electrical
|
Alteration/Remodel
|
Finaled
|
09/12/2017
|
|
:
Electrical
:
Heat tracing on storm drain piping for new parking ramp.
|
PREL201707994
|
Electrical
|
Alteration/Remodel
|
Finaled
|
08/29/2017
|
|
:
Electrical
:
Carbon monoxide-exhaust controls. (Job# 16-1963-80)
|
PRPS201707850
|
Sign, Permanent
|
New Sign
|
Finaled
|
10/11/2017
|
|
:
Sign
:
We are applying for (3) 36" x 36" Monument Signs at HealthPartners that the Uniform Sign Design had previously approved.
|
PRFS201707644
|
Fire Suppression System
|
New
|
Finaled
|
09/06/2017
|
|
:
Fire Suppression System
:
Provide sprinkler protection at the lowest level of a new ramp. Provide manual dry standpipes for all levels of the ramp.
|
PRAL201706316
|
Fire Alarm
|
Alteration/Remodel
|
Finaled
|
07/25/2017
|
|
:
Fire Alarm
:
Provide fire alarm system for Health Partners parking ramp. Separte electrical permit PREL201706309.
|
PREL201706309
|
Electrical
|
Alteration/Remodel
|
Finaled
|
07/24/2017
|
|
:
Electrical
:
Provide (electrical)/fire alarm system for parking ramp at Health Partners. Separate Fire Alarm Permit PRAL20176316.
|
PRAL201705743
|
Fire Alarm
|
Alteration/Remodel
|
Permit(s) Issued
|
07/05/2017
|
|
:
Fire Alarm
:
Adding: Smoke det, door holder. Removing: Heat det to lower level loading dock.
|
PREL201705740
|
Electrical
|
Alteration/Remodel
|
Permit(s) Issued
|
07/05/2017
|
|
:
Electrical
:
Adding: Smoke det, door holder. Removing: Heat det to lower level loading dock.
|
PRFS201704054
|
Fire Suppression System
|
Repair/Replace
|
Finaled
|
05/24/2017
|
|
:
Fire Suppression System
:
Replace all heads in building (42 dry; 2484 wet).
|
PREL201703562
|
Electrical
|
Repair/Replace
|
Finaled
|
05/10/2017
|
|
:
Electrical
:
Controls for new boilers, chillers, and VFD's for 3 AHU's
|
PRPL201702198
|
Plumbing
|
Repair/Replace
|
Finaled
|
04/05/2017
|
|
:
Plumbing
:
Remove one RPZ from service.
|
PREL201702028
|
Electrical
|
New
|
Permit(s) Issued
|
04/04/2017
|
|
:
Electrical
:
Install low voltage fire alarm wiring.
|
PRAL201702017
|
Fire Alarm
|
New
|
Finaled
|
04/04/2017
|
|
:
Fire Alarm
:
Reinstall fire alarm strobes in all restrooms and install new relay modules on each floor for freight elevator smoke curtain at Bloomington Corporate Center. Job#10627.
|
PRPL201701179
|
Plumbing
|
Alteration/Remodel
|
Finaled
|
09/07/2017
|
|
:
Plumbing
:
Remodel of existing restrooms. Adding new water riser. Installing new sump baskets.
|
PRFS201700768
|
Fire Suppression System
|
Other
|
Finaled
|
02/23/2017
|
|
:
Fire Suppression System
:
Add and Relocate fire sprinklers for the phase remodel of the restrooms Lower Level - 14th floor (4-9 Heads per floor). Remodel of the existing loading dock also part of the scope.
|
PRMH201700743
|
Mechanical/HVAC
|
Alteration/Remodel
|
Finaled
|
10/05/2017
|
|
:
Mechanical
:
Install (2) exhaust fans for underground parking ramp. Install (1) rooftop unit.
|
PRMH201700732
|
Mechanical/HVAC
|
Repair/Replace
|
Finaled
|
12/12/2017
|
|
:
Mechanical
:
See attached plan.
|
PRPL201700498
|
Plumbing
|
New
|
Finaled
|
02/21/2017
|
|
:
Plumbing
:
Plumbing work for new 7-story parking ramp with lower level enclosed garage.
|
PREL201700169
|
Electrical
|
Alteration/Remodel
|
Finaled
|
02/10/2017
|
|
:
Electrical
:
Remodel work at existing building, including remodel of restrooms, new chiller/mechanical equipment, new 350kw generator, new 3000A unit substation and remodel lower level office area/loading dock.
|